background image

92E1CJ20B (040309)

MODULAR CUBER
MACHINE A GLAÇONS MODULAIRE
MODULARER WÜRFELEISBEREITER
IJSBLOKJESMACHINE MET LOSSE OPSLAGBUNKER
FABRICADOR MODULAR DE CUBITOS DE HIELO
CUBETTATRICE MODULARE

INSTALLATION MANUAL

NOTICE D’INSTALLATION

INSTALLATIONSANLEITUNG 

INSTALLATIE VOORSCHRIFT

MANUAL DE INSTALACION

MANUALE PER L’INSTALLAZIONE 

FOR QUALIFIED INSTALLER ONLY

RESERVE A L’INSTALLATEUR 

FÜR DEN INSTALLATEUR

VOOR DE BEVOEGDE INSTALLATEUR

SOLAMENTE PARA INSTALADOR CUALIFICADO

SOLTANTO PER INSTALLATORI QUALIFICATI

IM-240DSME

IM-240XSME

Summary of Contents for IM-240DSME

Page 1: ...LO CUBETTATRICE MODULARE INSTALLATION MANUAL NOTICE D INSTALLATION INSTALLATIONSANLEITUNG INSTALLATIE VOORSCHRIFT MANUAL DE INSTALACION MANUALE PER L INSTALLAZIONE FOR QUALIFIED INSTALLER ONLY RESERVE A L INSTALLATEUR FÜR DEN INSTALLATEUR VOOR DE BEVOEGDE INSTALLATEUR SOLAMENTE PARA INSTALADOR CUALIFICADO SOLTANTO PER INSTALLATORI QUALIFICATI IM 240DSME IM 240XSME ...

Page 2: ...m and level foundation for the equipment 4 Allow 15 cm clearance at rear sides and top for proper air circulation and ease of maintenance and or service should they be required For air cooled model only allow 30 cm clearance at the right side 5 This appliance is not suitable for installation in an area where a water jet could be used and where dripping is not allowed 6 Do not place anything on top...

Page 3: ...with the two bolts and the two nuts provided See Fig 8 9 Place the Ice Chute lower or middle unit accessory and secure it to the Bracket with the two screws See Fig 8 10 Connect the leads with three way plug located in the lower unit wiring channel to the upper unit receptacle unplugged in the above step 6 Secure the leads using the plastic clamp provided Place the plastic cover in position See Fi...

Page 4: ... only be done by a qualified service engineer For the U K and the Republic of Ireland only The wires in the mains lead are coloured in accordance with the following code Green Yellow Earth Blue Neutral Brown Live As the colours of the wire in the mains lead of this appliance may not correspond with the coloured markings identifying the terminals in your plug proceed as follows The wire which is co...

Page 5: ...hem for a distinction between the gas line and the liquid line to prevent misconnection Apply some clean refrigerant oil of a suitable type to the surfaces of the Flare before connection and tightening Support the Access Valve with a spanner on the flat surfaces when tightening the nuts 8 Refit the Cap Nuts to a torque of 25 3 Nm 9 Check the Cap Nuts Port Caps and flare joints for gas leaks with a...

Page 6: ...or the Top Panel 5 Install refrigerant lines and make electrical connections for each Fan Motor as instructed under c and d Fig 21 Top Panel Upper Condenser Unit Lower Condenser Unit Screw Fig 20 Gasket Nut Bushing Cap Condenser Unit Fan Motor Wiring Cord Junction Box Fan Motor Leads inside Cord Grip Securing Hole Closed End Connector Inside Outside Wiring Cord Gasket Fig 19 Condenser Unit Fan Mot...

Page 7: ... in sequence a Compressor will start Hot Gas Valve open b Water Pan will fully open c Water Solenoid will open d Water Pan will start to close Hot Gas Valve closed e Water Pan fully closed Pump Motor will start f Water Solenoid will close Washing Switch Control Box Fig 24 Fig 25 Fig 23 Fig 22 Potable Water Inlet G3 4 Inlet Hose Drain Outlet R3 4 Outlet Hose Icemaker Water Supply Tap Inlet Hose 8 T...