INSTALLATION

When Installing This Product...

1.

Read these instructions carefully. Be sure to follow 
warning information carefully.

2.

Check the ratings given in the instructions and on the 
product to make sure the product is suitable for your 
application.

3.

Installer must be a trained, experienced flame 
safeguard control technician.

4.

After installation is complete, check out product 
operation as provided in these instructions.

WARNING

Explosion Hazard and Electrical Shock Hazard.

Can cause explosion, serious injury or death.

Turn off gas supply before beginning installation.

Disconnect power supply before beginning installation. 
More than one disconnection may be involved.

Mounting

Refer to the Integrated Valve Train Installation Instructions, 
form 66-1099, for instructions on mounting a V4297A in a 
Honeywell Integrated Valve Train System. Refer to the 
installation instructions packed with the Honeywell KTCPI001 
Visual Position Indicator for mounting instructions of the 
indicator.

WIRING

1.

Make sure all wiring agrees with all applicable local 
codes, ordinances and regulations. An opening is 
provided to accommodate rigid conduit or armored 
cable for line voltage operation. See Fig. 12.

2.

Check the power supply circuit to verify the voltage 
and frequency are correct for the valve.

3.

See Fig. 13 for typical V4297A wiring with the RM7800 
Burner Controller. Follow the burner manufacturer 
wiring diagram, when provided. Refer to the relay 
module wiring diagram for specific wiring terminal 
designations.

4.

Make wiring connections at the electrical terminations 
provided in the valve wiring compartment.

Fig. 12. Wiring compartment of V4297A SSOV. 

Fig. 13. Typical wiring diagram for V4297A SSOV.

G

L2

4

9

RM7800
(TYPICAL)

120 Vac

N

L

V4297A

M16540

GROUND

NEUTRAL

MAIN VALVE

LINE
VOLTAGE

Summary of Contents for V4297A Series

Page 1: ...alve body small applicable to five pipe sizes 3 4 in 19 mm 1 in 25 mm 1 1 4 in 32 mm 1 1 2 in 38 mm and 2 in 51 mm pipes Two valves with different capacities V4297A1005 1 in 25 mm internal opening small capacity V4297A1013 2 in 51 mm internal opening high capacity Two 1 4 in NPT upstream and one 1 4 in NPT downstream pressure taps and plugs Accepts C6097 Pressure Switch mounted directly to flange ...

Page 2: ...s listed Also this product is tested and calibrated under closely controlled conditions and some minor differences in performance can be expected if those conditions are changed Models V4297A1005 small body 1 in 25 mm internal opening small capacity V4297A1013 small body 2 in 51 mm internal opening high capacity Types of Gas Natural manufactured mixed or LP only Gas Train Pipe Size 3 4 in 19 mm 1 ...

Page 3: ...00 100 1 000 10 000 30 000 10 1 0 1 PRESSURE DROP IN WC FLOW CAPACITY cfh M16534 Propane sp gr 1 53 Natural Gas sp gr 0 64 LEGEND 100 100 1 000 10 000 30 000 10 1 0 1 PRESSURE DROP IN WC FLOW CAPACITY cfh M16535 Propane sp gr 1 53 Natural Gas sp gr 0 64 LEGEND 100 100 1 000 10 000 30 000 10 1 0 1 PRESSURE DROP IN WC FLOW CAPACITY cfh M16536 Propane sp gr 1 53 Natural Gas sp gr 0 64 LEGEND 100 100 ...

Page 4: ...al connections Current Draw V4297A1005 small capacity 120V 0 2A V4297A1013 high capacity 120V 0 5A Valve Opening Time 1 sec Valve Closing Time 1 sec Dimensions See Fig 10 and 11 Weight V4297A1005 8 lb 3 6 kg V4297A1013 14 lb 6 3 kg Replacement Parts BBA51315 Coil for V4297A1005 BBA51318 Coil for V4297A1013 Accessories Pipe Adapters 32000109 001 3 4 in NPT 32000109 002 1 in NPT 32000109 003 1 1 4 i...

Page 5: ...esign Certified Factory Mutual FM Approved KTCPI001 Visual Position Indicator required if used with pipe size larger than 3 4 in NOTE NOTE Some application codes such as NFPA require visual indication of the valve position as provided by the KTCPI001 Visual Position Indicator 2 51 5 127 5 1 2 140 5 5 8 143 2 1 2 64 1 1 2 38 2 51 2 3 4 70 1 2 13 5 3 4 147 5 5 8 143 9 229 M16541 TOP VIEW 2 51 5 127 ...

Page 6: ...uctions on mounting a V4297A in a Honeywell Integrated Valve Train System Refer to the installation instructions packed with the Honeywell KTCPI001 Visual Position Indicator for mounting instructions of the indicator WIRING 1 Make sure all wiring agrees with all applicable local codes ordinances and regulations An opening is provided to accommodate rigid conduit or armored cable for line voltage o...

Page 7: ...gas cock A 7 Run the V4297A Valve to is open position through the safety system then immediately de energize the system to close the V4297A Valve 8 Immerse a 1 4 in 6 mm tube vertically 1 2 in 13 mm into a jar of water 9 Slowly open the manual test petcock F 10 When the rate of bubbles coming through the water stabilizes count the number of bubbles appearing during a ten second period Each bubble ...

Page 8: ... terminal block make sure all appropriate contacts in the thermostat or controller limits and flame safeguard controls are closed If one or more are open determine the cause s correct the trouble and proceed 4 If there is proper voltage at the valve but the valve still does not open check for normal gas pressure 5 If the valve still does not open replace the valve If the valve does not close when ...

Reviews: