S7999B SYSTEM DISPLAY
65-0283—2
2
FEATURES
• Allows configuration of the R7999 ControLinks™
Controller.
• Allows monitoring of the R7999 ControLinks™
Controller.
• Allows monitoring of 7800 SERIES burner control.
• Allows monitoring of S7830 Expanded Annunciator.
• Allows monitoring and control of UDC2500/3200/3500
Universal Digital Controllers.
• Allows switching view between multiple burner systems.
• Dynamically locates attached burner systems (auto
seeks).
• Allows 4-20 mA firing rate hysteresis adjustment.
• Allows Actuator control accuracy adjustment.
• Allows off-line profile curve building.
• Allows programmable expanded annunciator terminal
naming.
• Allows burner system naming.
• Allows ControLinks™ R7999 EEPROM backup and
restore.
• Color 3.5 in. x 4.625 in. (5.7 in. diagonal) user interface
display.
• Touch screen.
• Two RS-485 communication ports (COM 1, COM 2).
• LED indicators:
• Power.
• EtherNet™ Communication traffic.
• Local Fuel/Air configuration port or System
Modbus™ communication.
• Modbus™ communication.
• Audio feedback.
• Flush mounting.
• Touch screen disable for screen cleaning.
• 12 Vdc power supply.
• Screen saver.
• Contrast control.
• Volume control.
• Real-time data trending analysis.
• Graphic user interface.
SOFTWARE UPGRADE
You can download new software for the S7999B through the
Internet. Downloading software should only be done when
recommended by Honeywell. This feature is intended to
permit field upgrades for bug fixes and to install new features.
Requirements for downloading new software:
• Ethernet connection for Internet access (RJ45 male
connector). Carefully insert the RJ45 connector into the
Ethernet jack in the lower right corner on the back of the
display to ensure no damage to the jack.
• Dynamic IP addressing (from DHCP server).
IMPORTANT
If these requirements can’t be met at the location of
the S7999B, this procedure should not be done or
the S7999B should be moved to a location where
these requirements can be met. Failure to satisfy
these requirements can result in the S7999B becom-
ing inoperable when the upgrade steps are followed.
The above requirements can be checked prior to execution of
the software upgrade procedure on the Ethernet Setup page
(see Advanced Setup section). On the Ethernet Setup page a
connectivity check can be performed to validate whether
access to the Honeywell server is possible.
The S7999B must be reset to initiate the download procedure.
Initial boot procedure of the device permits the user to enter
into Advanced Startup options within the first five seconds
after power up.
Follow these steps:
1.
Select the Advanced Startup Options button.
A Warning message is displayed. If you don’t want to
proceed with the software upgrade, you can cancel the
procedure at this time.
2.
Select OK to proceed.
3.
Select the “Force Application Update” checkbox.
4.
Deselect the “Use Existing Application” checkbox.
5.
Select the Continue button.
The software upgrade is automatic after the above steps. The
S7999B connects to the Honeywell server, which verifies the
configuration file, erases the old application and downloads
the new one.
The S7999B may have difficulty finding the new configuration
file at first. In this case, the procedure automatically starts
over again until it works.