Commissioning
This section gives the procedure for
commissioning the IDR repeater.
Commissioning consists of:
a. Preliminary checks.
b. Power-up checks.
3.1
Preliminary Checks
Carry out the following preliminary checks for
EVERY IDR repeater being commissioned,
prior to powering-up the system:
1
Check that all cables brought into the IDR
repeater have been terminated correctly.
The connection of external wiring is
described in
signal cabling and wiring must conform to
the appropriate local regulation.
2
Check that the address has been set
correctly as described in
2
net
network).
Only terminate the IDR
repeater power cables at
the fire control panel
after ALL preliminary
checks have been done.
ATTENTION
Observe precautions for
handling Electrostatic
Sensitive Devices