4. If you can’t use an air blower, use a brush with soft bristles to avoid scratching the equipment.
5. When you are done cleaning the equipment, put the side covers back in place, redo all RF and power
connections, and turn the equipment on. Follow the activation procedure.
2.2. Visual Inspection
Remove the side covers.
1. Verify if all the connections in the modules, as well as the RF connections in the equipment and
the irradiant system are correct.
2. Verify if rain water is coming through the RF cables or water dripping from the shelter’s ceiling.
3. Verify all the air inputs and outputs of the equipment to make sure that they are not blocked.
4. When you finish the visual inspection, put the side covers back.
2.3. Reading Verification
Make all the possible measurements through the instruments and take notes of the results. Compare the
obtained results with the quality control sheets, which come with the equipment. The monthly verification
of these measurements helps to prevent any abnormality that may occur.
Summary of Contents for EC702MP-BB3
Page 68: ...68 108 E Compact MP BB3 Series VGS Carrier Software Version 1 75 1 70 1 71 1 78 ...
Page 84: ...84 108 E Compact MP BB3 Series B220 BIPHASIC 220VAC 2 PHASE 110VAC GND ...
Page 85: ...85 108 E Compact MP BB3 Series M220 SINGLEPHASE 220VAC 1 PHASE NEUTRAL GND ...
Page 106: ...106 108 E Compact MP BB3 Series Section 8 Attachments ...
Page 108: ...108 108 E Compact MP BB3 Series ...