7.1 Orthopedic Frame
Chapter 7: Accessories
Page 7 - 2
Electrically Operated General Ward Bed
Operation and Maintenance Manual
(154588 REV 1)
7.1
Orthopedic Frame
Tools required:
None
Installation
1. Install the uprights (A) into the corner sockets of the bed (see figure 7-1 on
2. Install the parallel bars (B). Do not tighten the clamp at this time.
NOTE:
Allow the parts to float until the assembly is completed.
3. Install the cross bars (C). Position the bars as required.
NOTE:
Allow the parts to float until the assembly is completed.
4. Install the holders (D) and pulley supports (E). Position the items as
required.
5. Tighten all clamps securely.
Removal
Do the installation procedure in reverse order.