10
Maintenance schedule (Customer inspection)
84
Item
Procedure
Safety valve
Check safety valve tightness
System pressure
Check system pressure
Minimum pressure: 1,5 bar (cold)
Maximum pressure: see boiler plate
Fire extinguisher
Check fire extinguisher securing and seal
as well as hose and nozzle (according to
national standard)
Sensor barrier
Unscrew revision cover
Clean sensors on the inside of the
intermediate hopper with soft tissue on
the left and right
Ash storage
Ash has to be stored in a non-flammable,
air tight container till disposal.
Boiler room
Remove flammable materials, except
wood chips or pellets stored in a
appropriate container, from the operating
room
Fire protection
Check structural fire protection and fire
doors (e.g.: self-locking fire door)
Ignition pipe
Clean from the back with cleaning brush
10.3
Annually inspection
Annual inspection, at least every 3000 operating hours
Item
Procedure
Maintenance
Conduct system maintenance by authorised
personnel.
Drives and motors
Check
gear
motor
for
abnormal
or
conspicuous running noises by using the
aggregate test.
Summary of Contents for pelletfire 20/20
Page 1: ...OPERATING INSTRUCTIONS Log wood pellet heating system pelletfire 20 40 ...
Page 90: ...15 Annex 90 15 ANNEX 15 1 Additional boiler module Hydraulic recommendation 1 ...
Page 91: ...Annex 15 91 Hydraulic recommendation 2 ...
Page 92: ...15 Annex 92 15 2 Solar module Program 1 ...
Page 93: ...Annex 15 93 Program 2 ...
Page 94: ...15 Annex 94 Program 3 ...
Page 95: ...Annex 15 95 Program 4 ...
Page 96: ...15 Annex 96 Program 5 ...
Page 97: ...Annex 15 97 Program 6 ...
Page 98: ...16 Notes 98 16 NOTES ...
Page 99: ...Notes 16 99 ...