98
E.
Inspect and clean all components. See paragraph 5.7.7, Cleaning And In-
spection Guidelines.
Inspect oil seal, if inspection indicates replacement is required see para-
1.
graph 5.8.4.13.1, Oil Seals.
Inspect and measure clearance rings, If inspection indicates clearance
2.
rings require replacement see paragraph 5.8.7.2, Pump Clearance Ring
R&R.
Inspect and measure impeller, if inspection indicates impeller requires
3.
replacement see paragraph 5.8.4.6 (MBP), 5.8.4.7 (AP), or 5.8.4.8 (CBP).
If pump is an MBP and inspection indicated inducer replacement is re-
4.
quired see paragraph 5.8.4.5.
No need to inspect mechanical seal, O-rings, and gaskets as their re-
5.
placement is ALWAYS required.
Pump Head Installation
A.
Prepare pump head for installation.
Install new O-ring.
1.
a)
Lubricate O-ring. Refer to Table 20.
b)
Install new O-ring on pump head on gearbox side.
B.
Install pump head on gearbox, do not damage oil seal or pump shaft.
C.
Secure pump head to gearbox.
Install four washers.
1.
Install four (4) M12 x 1.75 full nuts.
2.
Using a 3/4-in (19 mm) wrench tighten (CW) four (4) M12 x 1.75 full nuts.
3.
D.
Using a cross pattern, torque nuts. Refer to Table 22 for recommended
torque values for fastener size and material.
With only the pump head installed on the pump, use the instructions in paragraph 5.8.4.9, Me-
chanical Seal R&R, and paragraph 5.8.4.6 (MBP), 5.8.4.7 (AP), or 5.8.4.8 (CBP) to install the seal
and impeller. If the pump is an MBP, install the inducer, see paragraph 5.8.4.5. Then install the
volute and test the pump as described in paragraph 5.8.4.3 or 5.8.4.4, Volute R&R.
5.8.4.12
RSD Pump Head R&R
As stated in paragraph 5.8.4.11, do not confuse oil or water leaks for a pump head failure. (See
AP/CBP/MBP Pump Head R&R on page 96 for full details.)
This procedure ONLY applies when the pump head requires removal from the gearbox. Prior to
performing this procedure, remove the RSD volute as described in paragraph 5.8.4.2, RSD Vol-
ute R&R. Then remove the inducer as described in paragraph 5.8.4.5, and the impeller as de-
scribed in paragraph 5.8.4.6, MBP/RSD Impeller R&R, and the mechanical seal as described in
paragraph 5.8.4.10, RSD Mechanical Seal R&R.
Refer to Table 36 for a list of tools and/or consumables required for this procedure.
Summary of Contents for AP
Page 2: ......
Page 28: ......
Page 71: ...59 Figure 19 One Piece Volute AP CBP MBP Figure 20 Three Piece Volute RSD...
Page 73: ...61 Figure 21 AP Pump Exploded View...
Page 74: ...62 Figure 22 CBP Pump Exploded View...
Page 75: ...63 Figure 23 MBP Pump Exploded View...
Page 76: ...64 Figure 24 RSD Pump Exploded View...
Page 77: ...65 Figure 25 Gearbox Exploded View All Except 3 74 1 GR...
Page 78: ...66 Figure 26 Gearbox Exploded View 3 74 1 GR...
Page 158: ...146 THIS PAGE INTENTIONALLY BLANK...
Page 174: ...C 12 THIS PAGE INTENTIONALLY BLANK...
Page 176: ...D 2 DATE HOURS RUN MAINTENANCE PROBLEM PART S USED REASON REPLACED INITIALS...