1-21
Typically, modules, power supplies, and fan trays are packaged in cartons. The packaging materials
include cartons, foam cushions, and anti-static bags.
To unpack and inspect a component:
1.
Use a utility knife to cut the straps on the carton. Open the carton and take the top foam cushion
out of the carton.
2.
Wear an ESD wrist strap and make sure the wrist strap is reliably grounded.
3.
Take the component out of the anti-static bag.
4.
Check the items in the carton against the packing list to verify that the items are as ordered.
Figure1-16 Unpacking a component packaged in a carton
Installation tools
Installation tools are required when installing the router. Prepare installation tools as required.
Summary of Contents for CR19000-20
Page 11: ...1 5 Figure1 1 Chassis dimensions...
Page 39: ...2 9 Figure2 7 Securing the router to the rack...
Page 61: ...4 2 Figure4 1 Slot arrangement...
Page 84: ...6 5 Figure6 4 Installing an air filter...
Page 97: ...8 9 Figure8 9 Removing a fan tray...
Page 103: ...8 15 Figure8 18 Securing the new power tray...
Page 131: ...11 7 Figure11 8 Routing AC power cords...