Chapter 5: Assembling Sidewall Sheets
Guidelines for Constructing Sidewall Sheets
1. Before bolting the sidewall sheets together, check for the proper gauge of steel for the first ring.
NOTE:
Higher gauge numbers denote the thinner materials. (For example, 20 gauge material is
thinner than 14 gauge.)
2. The first sidewall ring you assemble will be the top ring of the bin, using the lightest gauge of
sidewall.
3. Check the various gauges of the bin with the color code chart and begin building accordingly.
4. Select the proper gauge material and assemble all sidewall sheets with the left panel to the inside
with the right panel to the outside.
Figure 5-4
Constructing sidewall sheets
A
Left panel
C
Concrete foundation
B
Right panel
D
Sidewall sheet
PNEG-4936
36 Ft. TopDry Autoflow
45
Summary of Contents for TopDry Autoflow
Page 6: ...NOTES 6 PNEG 4936 36 Ft TopDry Autoflow...
Page 26: ...NOTES 26 PNEG 4936 36 Ft TopDry Autoflow...
Page 46: ...NOTES 46 PNEG 4936 36 Ft TopDry Autoflow...
Page 106: ...NOTES 106 PNEG 4936 36 Ft TopDry Autoflow...
Page 128: ...NOTES 128 PNEG 4936 36 Ft TopDry Autoflow...