Locating the Chutes
Use the following procedures to locate the starting position of the first chutes.
1. Starting from the first row of holes in the top sheet, measure down the “starting distance” for the bin.
2. Keep adding the required number of chutes, making sure to leave 8 in. between the chute bolt
holes.
Figure 9-17
Locating the Chutes
A
First hole on top sheet
C
Distance between chute bolt holes
B
Starting dimension for first chute
Sidedraw Chute Installation
Number of Rings
Starting Dimension
Number of Chutes
Horizontal Location For
First Chute
21
54 in.
21
Center between Stiffeners
20
42 in.
20
Center between Stiffeners
19
62 in.
18
Center between Stiffeners
18
50 in.
17
Center between Stiffeners
17
38 in.
16
Center between Stiffeners
16
58 in.
14
Center between Stiffeners
15
46 in.
13
Center between Stiffeners
14
34 in.
12
Center between Stiffeners
13
54 in.
10
Middle of Sheet
12
42 in.
9
Middle of Sheet
11
62 in.
7
Middle of Sheet
10
50 in.
6
Middle of Sheet
9
38 in.
5
Middle of Sheet
8
58 in.
4
Middle of Sheet
7
48 in.
3
Middle of Sheet
160
PNEG-4472
72 Ft Diameter Z-Tek Bins
Summary of Contents for 40-SERIES
Page 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...