Inside Ladder Placement
The inside ladder provides manway access from inside the bin.
What You Should Know
Begin by temporarily positioning the ladder (B) directly under the manway roof panel (A) for the correct
placement location. Mark or scribe this location where each side of the ladder’s vertical channels meet
the sidewall.
Figure 9-13
Positioning the ladder
A
Manway access
B
Ladder assembly
1. Install the right-hand starter bracket (C) to the top hole in the first sidewall ring, located closest to the
eave. Install a flange bolt (D), and secure with a flange nut (G).
2. Measure approximately 18-3/4 inches (E) to the left of the RH starter bracket (C), and install the LH
starter bracket (K) to the top hole in the first sidewall ring, located closest to the eave. Install a flange
bolt (D), and secure with a flange nut (G).
3. Temporarily position the ladder back into place, ensuring that the mating surface of each starter
brackets (C and K) are aligned with the inside mating surface of each vertical channel of the ladder
(B).
4. Field drill a second 3/8 in. hole (F) using the bottom hole in the starter brackets (C and K) as guides.
Install a flange bolt (D), and secure with a flange nut (G). Tighten hardware to the recommended
torque specifications. See
Bolt Torque Specifications, page 28
154
PNEG-4472
72 Ft Diameter Z-Tek Bins
Summary of Contents for 40-SERIES
Page 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Page 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...