Growatt ShineLimit
User manual
For more info, please download from http://server.growatt.com
+86 755 2951 5888
+86 755 2747 2131
www.ginverter.com
1) Before using the unit, please read this manual carefully.
Otherwise, if you don’t follow the steps described of the
instruction to use and cause any damaged,Growatt has the
right not to service you.
2) All the tasks described in this manual should be performed by
qualified personnel.
3) During installation, please don’t touch any inside part of this
unit besides terminals.
4) All wires connection of unit should be abided by the local
electric safety criterions.
5) If necessary, please contact specified installer
Item
Name
Description
A
PV panel
Inverter PV panel
B
Inverter
PV Inverter with ShineRFStick
C
Loads
User loads
D
SP-CT
ShineLimit detecting meter
E
Grid
220V public grid
F
ShineLanBox
ShineLimit controller
G
Router
Unpacking
1.1 Unpacking ShineLink, and check the package
device list:
·
Safety precaution
·
Product Description
Growatt ShineLimit0 is the zero output control system for
pv plant. It use RF wireless devices to communicate, like
ShineRFStick and SP-CT, control the pv inverter active power
by the power of loads to enable zero output to Grid, and can be
monitored from the net server by RJ45. The System Diagram
as bellow:
System Diagram:
Step1.
Item
Name
Quantity
A
ShineLanBox
1
B
ShineRFStick
1
C
Network
1
D
Power adapter
1
E
Fixing screws
4
F
Wall plastic posts
2
G
User manual
1
1.2 Unpacking SP-CT, and check the package device
list:
Item
A
B
C
D
E
F
--
--
Description
Growatt SP-CT
Antenna
Sensor (water-proof terminal)
M5*30 pan head screw
Expansion screw
W
Sucker antenna this is for SP
(Storage machine)
arranty card
Manual
Quantity
1
1
1
2
2
1
1
1
1.3 SP-CT SE
1.3.1 Nameplate description
There is some essential information such as product model,
specifications and approva
l on the Nameplate in the
rear of SP-CT:
Installation
Step2.
2.1 General precautions
A. Safety measures
·
Qualified personnel can operate only
·
The kids, the disable, non-professional are
not allowed to close.
SP-CT High voltage danger
!
SP-CT Ground wire connection
Ensure the SP-CT ground wire is properly
earthed
Symbol
Description
Risk of electric shock!
Ground point
Alternating current
CE Mark, which means it satisfies CE criterion
RCM Mark, which means it satisfies RCM criterion.
B. Symbol used of SP-CT
C
.
Device install place please refer to the system Diagram
above.About the distance between the ShineLanBox with the
ShineRFStick and SP-CT, the maximum linear distance is
200m if there is no obstructions between then; the maximum
distance is 50m if there is one wall between then;
the maximum distance is 20m if there are two walls between
then.
2.2 Install SP-CT
2.2.1 Basic requirements of mounting
A
time. ( refer to the chapter 3.3 to know the precise weight)
B Mount on where has enough space for SP-CT ( refer to the chapter 3.3)
.
C Do not mount on flammable construction materials
.
D Designed with IP65 degree for indoor or outdoor applications .
E Ambient humidity range: 0~95%
.
F Ambient temperature range: -25
℃~
60
℃
.
G Vertically installation or tilt angle 15-dgress installation is ok, as the
chart 5.1
.
Mount on solid surface and can accommodate weight of SP-CT long
.
H
To make sure operate and maintain available the unit, please leave
enough space for SP-CT.
2.3 Installation guide
2.3 Installation layout
.1
2.3 Mounting
.2
1). Mark locations of the hole of SP-CT.
2). Insert 2 expansion screws in the holes.
3). Screw 2 screws( M5) firmly.
4). Place the SP-CT on the 2 screws .
Installation layout of storage energy system with SP-CT should
be as following feature shows .
Note: The recommend distance between stored-energy machine
and SP-CT is less than 50 m.
I
function .
Do not install where is near to Radio or machine which has wireless
J Do not install the place where the children can reach.
2.4 Wires connection
2.4 AC auxiliary power wires connection
.1
Preparation:
(1) Ensure the grid voltage is 230VAC or 240VAC, frequency
is 50/60Hz single phase.
(2) Connection mode:
a) Type I:Connect the AC terminal of SP-CT to the AC breaker
of power distribution cabinet.
b) Type II:Press the AC terminal (British standard) of SP-CT
on the nearby socket. Because of installation outside,
the socket should be water-proof.
Caution:Ensure the utility phase of SP-CT position is same
with stored-energy machine and PV inverter phase position.
Type I
Typ II
Note: Type II installation is mainly suitable for British
standard area.
Green indicator solid on
Green indicator flash
Red indicator solid on
Working normal
In pair status
Fault e.g L and N connected
reversely or GND wire unconnected