GMV5 DC INVERTER VRF UNITS SERVICE MANUAL
27
Part 2 Material Selection
I. Requirement for Selecting Construction
Materials
The materials, equipment and instruments used during air conditioning engineering construction
must have certifications and test reports.
Products with fireproof requirements must be provided with fireproof inspection certificates and must
meet national and relevant compulsory standards.
If environmentally-friendly materials are to be used as required by customers, all such materials
must meet national environmental protection requirement and be provided with relevant certificates.
II. Requirement for Selecting Major Materials
1. Copper pipe
a. Material requirement: Dephosphorization drawing copper pipe for air conditioners
b. Appearance requirement: The inner and outer surface of pipe should be smooth without pinhole,
crack, peeling, blister, inclusion, copper powder, carbon deposition, rust, dirt or severe oxide film, and
without obvious scratch, pit, spot and other defects.
c.
Test report: Certifications and quality test reports must be provided.
d. The tensile strength must be at least 240 kgf/mm².
e. Specifications requirement
R410A Refrigerant System
OD (mm/inch)
Wall Thickness (mm)
Model
Φ
6.35(1/4)
≥0.8
0
Φ
9.52(3/8)
≥0.8
0
Φ
12.70(1/2)
≥0.8
0
Φ
15.9(5/8)
≥1.0
0
Φ
19.05(3/4)
≥1.0
0
Φ22.2(7/8)
≥1.2
1/2H
Φ25.40(1/1)
≥1.2
1/2H
Φ28.60(9/8)
≥1.2
1/2H
Φ31.80(5/4)
≥1.3
1/2H
Φ34.90(11/8)
≥1.3
1/2H
Φ38.10(12/8)
≥1.5
1/2H
Φ41.30(13/8)
≥1.5
1/2H
Φ44.5(7/4)
≥1.5
1/2H
Φ51.4(7/4)
≥1.5
1/2H
Φ54.1(17/8)
≥1.5
1/2H
f.
After the inner part of the copper pipe is cleaned and dried, the inlet and outlet must be sealed
tightly by using pipe caps, plugs or adhesive tapes.
2. Condensate water pipe
a. Pipes that can be used for air conditioner drainage include: water supplying UPVC pipe, PP-R
Summary of Contents for GMV-224WM/B-X
Page 1: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL T1 R410A 50 60Hz GC201508...
Page 27: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 24...
Page 29: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 26 V Construction Organization Process...
Page 38: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 35...
Page 47: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 44 GMV 504WM B X GMV 560WM B X and GMV 615WM B X...
Page 156: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 153 low press ure air pipe...
Page 158: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 155 2 Low exhaust temperature protection E2...
Page 160: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 157...
Page 161: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 158 5 System refrigerant lacking protection U4...
Page 162: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 159 6 System high pressure ratio protection J8...
Page 163: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 160 7 System low pressure ratio protection J9...
Page 165: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 162 11 Pressure sensor fault...
Page 224: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 221 2 Model GMV 335WM B X Exploded View...
Page 242: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 239...
Page 248: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 245 Click Finish...
Page 254: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 251 Click Next Installing...
Page 255: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 252 Click Close...
Page 272: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 269...
Page 287: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 284 1 4 2 5 Communication Debug...
Page 297: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 294...
Page 304: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 301...
Page 307: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 304...
Page 349: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 346...
Page 375: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 372 JF00302751...