6. 

Assembly above ground 

 
When installing the tanks above ground it is important to ensure that they are completely emptied when 
there is any danger of frost. Furthermore, the tanks must be installed on an appropriate level and 
compacted surface that is free from sharp objects and stones. Notice must be taken when installing the 
tanks that the total weight when filled will be 1,350 kg. The tanks should also be installed in a shaded 
area. When the tanks are to be installed in a closed room, it is necessary to ensure that there is a floor 
drainage system on hand. The tanks are not designed to work under pressure and therefore it is 
important to ensure that the overflow outlet has the same diameter as the inlet. 

6.1 

Joining multiple vessels 

The coupling of two or more tanks is achieved by means of assembly areas moulded into the bases of the 
tanks using GRAF special seals and canalisation pipes. The openings are only to be undertaken with the 
special GRAF core drills (hole saw) in the appropriate sizes. It is important to note that the distance 
between the tanks is a minimum of 10 cm. The pipes must extend into the tank at least 20 cm. If more 
than two tanks are to be connected to one another then in addition to the lower connection (inlet) there 
must also be an upper connection to ensure ventilation. 

6.2 

Laying connections 

The connection of the inlet and overflow is by means of the pre-drilled openings of the tank or by means 
of the pre-molded connection points intended for opening.    

All the suction and pressure control lines must be installed and connected 

above

  the maximum water 

level. 

 
 

7. 

Service and maintenance 

 
The system as a whole has to be checked for leaks, cleanliness, and stability at least every three months. 

The system as a whole should be maintained every 5 years. In doing so, all system components have to 
be cleaned and checked for functionality. Maintenance works should be conducted as follows: 

 

empty tank completely 

 

remove immovable residua using a pressure washer through the tank head 

 

remove all contaminations from the tank 

 

check all installation parts for proper seat 

Otto Graf GmbH – Carl-Zeiss-Str. 2-6 – D-79331 Teningen – Tel.: 0049/(0)7641/589-0 – Fax: 0049/(0)7641/589-50 
GRAF SARL – 45, Route d´Ernolsheim – F-67120 Dachstein Gare – Tel.: 0033/388497310 – Fax: 0033/388493280 
GRAF Iberica – C/Marquès de Caldes de Montbui, 114 baixos – ES-17003 Girona – Tel.: 0034/872032283 – Fax: 0034/872032284 
GRAF Ltd – Maidstone, Kent – UK-ME16 8Ry – Phone: +44 (0) 16 22 68 65 50 

Status: May 2009 

Summary of Contents for RainHarvest Systems Top-Tank 323002

Page 1: ...g Any missing instructions must be requested directly from us A complete check of all the items components for possible damage must be carried out before the assembly or installation begins The installation must be carried out by a professional firm Table of Contents 1 GENERAL NOTES 2 1 1 Safety 2 1 2 Identification obligation 2 2 INSTALLATION SET UP REQUIREMENTS 2 2 1 Assembly above ground 2 3 TR...

Page 2: ...an accidental connection to the drinking water network even after years Even when there are correct labels irritations are possible e g through children That is why all tapping points of process water have to be installed with child proof valves 2 Installation set up requirements 2 1 Assembly above ground The tanks must be installed on an appropriate level and compacted surface that is free from s...

Page 3: ...f the inner seat recess Before the second half of the tank is set in position the seal and the seat recess of the upper half must also be well coated with the lubricating soft soap During the assembly it is important to ensure that the seal does not slip out of the seat recess To secure the two halves the connection clips are fitted first in a counter clockwise direction and then in a clockwise di...

Page 4: ... into the tank at least 20 cm If more than two tanks are to be connected to one another then in addition to the lower connection inlet there must also be an upper connection to ensure ventilation 6 2 Laying connections The connection of the inlet and overflow is by means of the pre drilled openings of the tank or by means of the pre molded connection points intended for opening All the suction and...

Reviews: