Installation
12
3A6586D
7.
Connect wiring (not included) to X1 and X2 and a
ground wire to the grounding bar. This wiring is for
connection to the pump.
NOTE:
The other wires shown in
Figure 9
(H3, X3) are
connected at the factory and are not required for con-
necting the transformer to the pump.
8.
Run the wiring to the pump out through one of the
punch-outs in the side of the transformer cover. A
cord grip or conduit connection (not included) must
be used where wiring passes through the
punch-out.
9.
Reattach the front cover using the four screws
removed in step 3.
10. Connect the wiring from the transformer into termi-
nals 4T2 and 6T3 inside the junction box and attach
the ground wire to one of the two ground terminals
inside the junction box as described in
Connect
Power
.
Install Vented Oil Cap Before
Using Equipment.
The driver gear-box is shipped from the factory pre-filled
with oil. The temporary unvented cap prevents oil leaks
during shipment. Before use, this temporary cap must
be replaced with the vented oil cap supplied with the
equipment.
NOTE:
Prior to use, check oil level. Oil level should be
half way up the sight glass.
Fluid Hose Connection
Refer to
Figure 1
on page
Attach the fluid hose (not supplied) to the check valve
fluid hose connection (L).
NOTE:
Be sure all components are adequately sized
and pressure rated to meet the system’s requirements.
F
IG
. 9: Transformer Wiring Connections
H3 X3
H2 X2
H1 X1
Connections to Pump
Grounding Bar
Connections from Power Supply
F
IG
. 10: Unvented and Vented Oil Caps
Unvented
Cap
Vented Cap
Vented cap attached here where shipped.