Commissioning
English, Revision 01, Date: 14.04.2009
8
4
Commissioning
After mounting or changing the antennas, a position calibration is recommended. For
further information please see chapter 6.1.2 on page 12 and chapter 7.4.4.18 on page
32. The position calibration has to be carried out for each antenna individually.
NOTE!
Only by processing this positioalibration the interpreter is able to
calculate and display the deviation in mm.
For a position calibration the following things are required:
correct positioning of the antenna. I.e. its position has to be the same as the one
set in the interpreter (see also 6.1.2 on page 12 and 7.4.4.17 on page 31)
a guide wire with a rated current (if possible 10 kHz)
The calibration can be started by using the CAN bus or the serial interface. During this
procedure the antenna has to be moved from left to right in a certain area, being two
times mounting height above the wire (see 7.4.4.18 on page 32 and Figure 5 on page
14).