![Glowworm EASICOM 3 25s Installation And Maintenance Instructions Manual Download Page 32](http://html.mh-extra.com/html/glowworm/easicom-3-25s/easicom-3-25s_installation-and-maintenance-instructions-manual_2234649032.webp)
32
Installation and maintenance instructions EASICOM 3 0020238426_04
–
Clearance for the ignition electrodes: 3.5 to 4.5 mm
6.
Make sure that the seal
(5)
is free from damage.
▽
If necessary, replace the seal.
12.10 Cleaning the condensate tray
1.
Switch off the product via the main switch.
2.
Close the gas isolator cock.
3.
Remove the front casing. (
C
A
B
1
D
2
4.
Remove the screw
(1)
.
5.
Push the clip upwards.
6.
Remove the flue gas pipe
(2)
.
1
7.
Using water to clean the condensate tray
(1)
.
◁
The water runs out into the condensate siphon.
12.11 Cleaning the condensate siphon
C
2
3
1
A
B
1.
Unclip the lower section of the siphon
(1)
from the up-
per section of the siphon
(2)
.
2.
Remove the float
(3)
.
3.
Flush out the float and lower section of the siphon with
water.
4.
Fill the lower section of the siphon with water up to 10
mm below the upper edge of the condensate discharge
pipe.
5.
Re-insert the float
(3)
.
Note
Check whether the float is present in the
condensate siphon.
6.
Clip the lower section of the siphon
(1)
into the upper
section of the siphon
(2)
.
12.12 Installing the gas-air mixture unit
1.
Install the burner.
2.
Install the gas-air mixture unit.
3.
Tighten the screws in a cross-wise pattern until the
burner flange fits closely and uniformly onto the mat-
ing surfaces.
–
Tightening torque: 7 Nm, if a torque spanner is
available
4.
Install the air intake pipe.
5.
Install the flue pipe.
12.13 Draining the product
1.
Close the service valves of the product.
2.
Start check programme P.05 (
Check programmes
–
Overview (
3.
Open the draining cock.