background image

Operating & Maintenance Manual

Glasdon Buildings

Operating & Maintenance Manual

Glasdon Buildings

Operating & Maintenance Manual

Glasdon Buildings

Operating & Maintenance Manual

Glasdon Buildings

Operating & Maintenance Manual

Glasdon Buildings

Glasdon U.K. Limited

Preston New Road 

BLACKPOOL

Lancashire

FY4 4UL
Tel: (01253) 600410

Fax: (01253) 792558

e-mail: [email protected]

www.glasdon.com

Summary of Contents for Beacon

Page 1: ...on Buildings Operating Mainten Glasdon Bui Operating Maintenance Manual Glasdon Buildings Operating Maintenance Manual Glasdon Buildings Glasdon U K Limited Preston New Road BLACKPOOL Lancashire FY4 4UL Tel 01253 600410 Fax 01253 792558 e mail sales glasdon uk co uk www glasdon com ...

Page 2: ...and future care of your product Contents Chapter 1 Installation Chapter 2 Electrical Installations Chapter 3 Base Fixing Guidelines Chapter 4 Future Care of Your Product Chapter 5 Handling Moving Your Product Should you require any further assistance please contact us on tel 01253 600410 fax 01253 792558 or email sales glasdon uk co uk 2 ...

Page 3: ...tions In such cases the items will be supplied loose within the Building ready for simple site fitting by yourselves using the instruction sheet enclosed In the event that installation of your Glasdon Building does not take place at the time of delivery suitable temporary storage arrangements must be made by yourselves to prevent damage being sustained either by adverse weather conditions or other...

Page 4: ...ly be raised slightly above the surrounding ground level Base Fixing Detail 82mm composite wall panel Cover cap Expanding anchor bolt Flat level and square concrete base by customer Treated softwood bearers at 300mm spacing Treated softwood plinth Aluminium framework Mastic seal by others 125 45 132 F F L 20 94 44 136 Composite insulated floor panel with heavy duty vinyl covering and vapour barrie...

Page 5: ...e raised slightly above the surrounding ground level Base Fixing Detail 42mm composite wall panel Cover cap Expanding anchor bolt Flat level and square concrete base by customer Treated softwood bearers at 300mm spacing Treated softwood plinth Aluminium framework Mastic seal by others 45 20 94 90 Floor panel with heavy duty vinyl covering and insulation vapour barrier to underside 44 300 Treated s...

Page 6: ...ase fixing by our customers is accomplished using the expanding anchor bolts supplied Refer to the base fixing instructions supplied with the fixings for correct installation in accordance with the manufacturer s recommendations Finally apply an external mastic seal to the perimeter of the building 63 45 125 35 97 95 300 45 Plastic cover cap Flat level and square concrete base by customer 95 x 45m...

Page 7: ...d to BS EN 206 1 The base should be flat level and square and preferably be raised slightly above the surrounding ground level Base Fixing Base fixing by our customers is accomplished using the expanding anchor bolts supplied Refer to the base fixing instructions supplied with the fixings for correct installation in accordance with the manufacturer s recommendations Finally apply an external masti...

Page 8: ...ace the base should be a minimum of 125mm concrete on to well consolidated hardcore The concrete should be of minimum C20 25 grade in accordance with BS8500 Concrete The Complementary British Standard to BS EN 206 1 The base should be flat level and square and preferably be raised slightly above the surrounding ground level Base Fixing Detail Base Fixing Base fixing is recommended for all installa...

Page 9: ...e care 0 8 8 8 5 6373 6 6 8 4 55 or Roof 5 3 8 55 8 880 8 87 37B5 8 637 7 7 5 55 5 4 37 7 7 5 55 8 12 7 5 8 2 6895 3 Beacon Warrior Boxer Olympic PRODUCTS INTERNAL EXTERNAL SURFACES GLAZING Aluminium Framework External GRPWalls or Roof Plastic Coated Walls or Roof CottonVinyl or Laminate InternalWalls Flecked Paint Internal Walls GRP Internal Walls Ceiling Toughened Glass or Thermoplastic Beacon t...

Page 10: ...fore cleaning the glazing film and do not attempt to push out any surface defects during this curing period Wash with a sponge and warm water containing a mild soapy detergent and rinse immediately with clean water Air Conditioning Systems If an Air Conditioning System is installed in your Building the commissioning together with a 12 month maintenance and service agreement via a third party provi...

Page 11: ...106C E DO NOT USE CHAINS OR ROPES TO LIFT E DO NOT RUSH ANY PART OF THE LIFT E IF IN DOUBT PLEASE ASK Building sizes of 3 66 x 2 44m and above Building sizes up to 3 66 x 2 44m Position the slings at each corner of the Building on the underside of the panel base perimeter radius Position the slings at each corner of the Building on the underside of the panel base perimeter Position the slings in t...

Page 12: ...e slings produces a crushing effect upon the roof of the Building Slings must be seated at each end of the Building and positioned approx 250mm from the corners for maximum stability Always tension the slings before tying back and place the tie back ropes at low level to prevent the slings from slipping inwards or outwards as indicated on page 6 Small Buildings may require tighter roping Too much ...

Page 13: ...istance please contact us on tel 01253 600410 fax 01253 792558 or email sales glasdon uk co uk In accordance with our policy of continuous development and improvement we reserve the right to make changes in design and specification without notice Glasdon UK Limited products are manufactured under license worldwide and various components of the models are patented and design registered Glasdon U K ...

Reviews: