19
8.
Turn off main air supply and disconnect air line from
the system.
9.
Generously coat the exposed transfer pump shafts
with lithium grease.
10.
Coil the heated hoses with a minimum four foot
diameter to avoid kinking and subsequent damage to
the internal electrical wiring.
11.
For gun shut down, follow the procedure from the
gun manual.
12.
The length of time a system is shut down, and the
climate conditions it’s stored in will determine how
often the system should be purged and refilled.
Usually every 2 - 4 weeks the following procedure
should be followed.
Purge and Refill Procedure
1.
Connect the main air line to the system.
2.
Adjust main air regulator to 20 psi.
3.
Adjust transfer pump regulators to approximately 40 psi.
4.
Remove the side blocks from the gun.
Section 2 - Operation: Shut-Down Instructions
PROBLER P2
Summary of Contents for Guardian A5-6000 IP
Page 26: ...24 Section 3 General Information Assembly Drawings GC1751 Generic System Schematic...
Page 27: ...GC1751 System Schematic 220V Single Phase 25 Section 3 General Information Assembly Drawings...
Page 37: ...Section 4 Safety Information Notes 35...