25
Swiss Lifting Solutions
If the device can no longer be used, it must be disposed of in an environmentally safe manner. Lubricants, such as oils and greases, must
be disposed in accordance with the applicable waste law. Metals and plastics are to be recycled.
4.3 Disposal
* replace if worn
** replace at the latest in general overhaul
Components of LP models, all types
Check for wear *
Replace
Brake
x
Motor shaft
x
Gear teeth
x
Roller bearing
x
Sealings
x
Chain
x **
Chain wheel, chain guidance
x
Suspension
x
Load hook
x
Contactor, limit switch
x
Table 4-2 General overhaul
On reaching the theoretical full load cycles (no later than 10 years for recording without BDE), a general overhaul should be performed.
This enables the equipment to continue operating safely for a further period of time. Components must be checked or replaced in ac-
cordance with table 4-2. The checking and release for the further use must be done by a specialist company authorised by the manufactu-
rer or by the manufacturer themselves.
The inspector determines:
• What new theoretical full load cycles are possible.
• The max. period until the next general overhaul.
This data should be recorded in the inspection pass.
4.2 General overhaul
Number of cycles per
working day
<= 15
(15)
<= 30
(30)
<= 60
(60)
<= 120
(120)
<= 240
(240)
<= 480
(480)
<= 960
(960)
<= 1920
(1920)
Load spectrum
Annual use in full load cycles
Q2 = 0.50
400
800
1 600
3 150
6 300
12 500
25 000
50 000
Q3 = 0.63
800
1 600
3 150
6 300
12 500
25 000
50 000
100 000
Q4 = 0.80
1 600
3 150
6 300
12 500
25 000
50 000
100 000
200 000
Q5 = 1.00
3 150
6 300
12 500
25 000
50 000
100 000
200 000
400 000
Table 4-1 Annual use (208 working days / year)