Inspection of the installed door system
10 Inspection of the installed door system
10.1 Measures to prevent and secure hazardous areas
X
Check protective earth connection to all metal parts that can be touched.
X
Perform a safety analysis (risk analysis).
X
Check the function of safety sensors and movement detectors.
10.2 Installation checklist Slimdrive SLT
no.
Test
in
On page Completed
1
All cables laid correctly for the installation of the Slimdrive SLT?
–
–
2
Track mounted?
3
Angled floor guide/continuous floor guide installed?
4
Moving leaf installed?
5
Drive components installed?
6
Tooth belt mounted?
7
Tooth belt locking mechanism (optional) and control unit connected?
–
–
8
Safety devices mounted?
9
Switches/push buttons installed and correctly connected?
10
Programme switch installed?
11
Transformer ground fitted?
12
Ground connection established?
13
230/115 V connection established?
14
Cover earthing connected?
15
Supports for cover installed?
–
–
16
Cover safety ropes fitted?
–
–
17
Safety analysis carried out?
–
–
18
Deviations of the door system checked in accordance with safety analysis? –
–
19
Are all components mounted in accordance with the following
instructions:
–
–
20
à
Pre-installation instructions Slimdrive SLT
–
–
21
à
Installation instructions SLT – girder section and side panel
–
–
22
à
Pre-installation instructions profile system leaves and side panel
–
–
23
à
Installation instructions protective leaf for sliding door drives
–
–
24
à
Installation instructions safety leaf
–
–
25
Was the type plate for the Slimdrive SLT adhered instead of the type
plate for the Slimdrive SL?
26
Type plate added to the sliding door system?
Notes:
à
Only relevant for Germany and within the scope of validity of
DIN 18650
à
The type plate may only be attached to the sliding door system if
assembly was also checked for correct completion according to the
GEZE specifications using the check list.