Assembly
GEDA
®
3700 Z/ZP
Assembly Instructions
Page 52 of 60
ML034 GB 2017 / 11
The cable carriage is fully at the
bottom.
Guide the travelling cable (1) over the
cable roller of the cable carriage (8) to
the cable holder (9) on the trolley.
Fold down the cover of the cable roller
and firmly attach.
Pull any remaining travelling cable
towards the mast over the central
feeder.
The cable must be installed so that the
side with the cable identification is
located on the outside of the cable
pulley / cable carriage.
Route the other side of the cable loop at the mast downwards to the
cable box and attach it using suitable fasteners in regular intervals.
Tension relief with weather protection
must be installed at the plug
connection of the travelling cable from
the cable box and travelling cable
extension.
Position of the pull relief between the cable
box and central feeder on the extension
plug.
Place excess travelling cable in the cable box.
4
9
8
1