Assembly Instructions
6.6
Assembly procedure
The installation plan shows the basic assembly stages and their
chronological sequence. However, installation is always carried out in
accordance with the detailed instructions in this manual and, as
necessary, the released assembly drawings. Depending on the work
equipment available / number of installation engineers, work may be
carried out in parallel or the sequence of the installation steps may be
changed. If the sequence is changed, the amended installation plan must
be checked by the operating company to ensure that it is sensible and that
there are no potential hazards and must be subsequently approved.
GEDA 3700 Z/ZP assembly schematic
Erecting the base unit
Aligning the base unit
anchor the foot section to the ground
Cordon off/identify the hazard area and
assemble the 1.1 m base enclosure (optional)
Mount/position the roof for swivelling.
Installing the mast assembly aid (optional)
Electrical connection
Connecting / switching on the electrical components
Insert mains plug at the building site main cabinet
Assembly / anchoring the mast
Install the mast sections
Install the mast ties
Align the mast
Install the travelling cable guides
Position EMERGENCY top limit switch bar
Cable carriage option
Assembling the cable carriage
Assembling the central feeder
Routing the travelling cable over the cable carriage
Secure the loading positions with the landing level safety gates
Position the limit switch approach bar, landing level
Installing the landing level safety gates
Assembly of the electric modules
Inspection after assembly
Check the machine for initial commissioning
Before commissioning
each time, check the machine
Instruct authorized personnel on how to use.