7.4 Maintenance during running-in period
The machine has been tested and checked on the manufacturer's premises, therefore it is deemed
to be ready for commissioning.
However, on the Customer's premises, all of the following running-in activities must be carried out:
Sheet
No.
Maintenance
frequency
Job location
Activity
00-[a]
00-[b]
After 50 hours of the
running-in period
Machine in general
- Check for presence of
abnormal noise and
vibrations
- Check protections and safety
devices
F [a]
After 500 hours
of the running-in
period
Lubrication system
- Check and top up the oil level
if needed
L [a]
After 200 hours
of the running-in
period
Drive
- Check belt tension
7.5 Planned routine maintenance during operation
7.5.1 General Information
Below are the tables and descriptions of periodic maintenance activities that should be carried out to
ensure the efficient and safe maintenance of the machine.
The values apply to normal use of the machine; heavy-duty operating conditions or particularly
abrasive/aggressive products may significantly reduce the service life of certain parts, which therefore
require more frequent checking.
In the event of malfunction of the machine or abnormal noise, it is advisable to identify the components
that may be the cause of the noise and ensure that they are correctly installed and suitably tightened,
replacing any worn parts as needed.
WARNING:
The following Periodic Maintenance tables refer to normal operating conditions but in no way
constitute a guarantee as to the minimum life of the consumable components mentioned,
only an indication of the average life.
Special conditions, such as high operating pressures, steam sterilisation and frequent
washing, as well as incorrect operating procedures, can significantly affect the life of the
machine and its components, therefore the intervals for maintenance of the compression
head components vary considerably.
Routine maintenance is normally performed at the following intervals: