The operands available for this relay are listed alphabetically by types in the following table.
Table 5–15: G60 FLEXLOGIC OPERANDS (Sheet 1 of 9)
OPERAND TYPE
OPERAND SYNTAX
OPERAND DESCRIPTION
CONTROL
PUSHBUTTONS
CONTROL PUSHBTN 1 ON
CONTROL PUSHBTN 2 ON
CONTROL PUSHBTN 3 ON
CONTROL PUSHBTN 4 ON
CONTROL PUSHBTN 5 ON
CONTROL PUSHBTN 6 ON
CONTROL PUSHBTN 7 ON
Control pushbutton 1 is being pressed
Control pushbutton 2 is being pressed
Control pushbutton 3 is being pressed
Control pushbutton 4 is being pressed
Control pushbutton 5 is being pressed
Control pushbutton 6 is being pressed
Control pushbutton 7 is being pressed
DIRECT DEVICES
DIRECT DEVICE 1On
↓
DIRECT DEVICE 16On
DIRECT DEVICE 1Off
↓
DIRECT DEVICE 16Off
Flag is set, logic=1
↓
Flag is set, logic=1
Flag is set, logic=1
↓
Flag is set, logic=1
DIRECT INPUT/
OUTPUT
CHANNEL
MONITORING
DIR IO CH1 CRC ALARM
DIR IO CH2 CRC ALARM
DIR IO CH1 UNRET ALM
DIR IO CH2 UNRET ALM
The rate of direct input messages received on channel 1 and failing the CRC
exceeded the user-specified level
The rate of direct input messages received on channel 2 and failing the CRC
exceeded the user-specified level
The rate of returned direct input/output messages on channel 1 exceeded the
user-specified level (ring configurations only)
The rate of returned direct input/output messages on channel 2 exceeded the
user-specified level (ring configurations only)
ELEMENT:
100% stator ground
100% STATOR STG1 PKP
100% STATOR STG1 OP
100% STATOR STG1 DPO
100% STATOR STG2 PKP
100% STATOR STG2 OP
100% STATOR STG2 DPO
100% STATOR PKP
100% STATOR OP
100% STATOR DPO
Stage 1 of the 100% stator ground element has picked up
Stage 1 of the 100% stator ground element has operated
Stage 1 of the 100% stator ground element has dropped out
Stage 2 of the 100% stator ground element has picked up
Stage 2 of the 100% stator ground element has operated
Stage 2 of the 100% stator ground element has dropped out
The 100% stator ground element has picked up
The 100% stator ground element has operated
The 100% stator ground element has dropped out
ELEMENT:
Third harmonic
neutral undervoltage
3RD HARM NTRL UV PKP
3RD HARM NTRL UV OP
3RD HARM NTRL UV DPO
Third harmonic neutral undervoltage element has picked up
Third harmonic neutral undervoltage element has operated
Third harmonic neutral undervoltage element has dropped out
ELEMENT:
Accidental
energization
ACCDNT ENRG ARMED
ACCDNT ENRG DPO
ACCDNT ENRG OP
The accidental energization element is armed
The accidental energization element has dropped out
The accidental energization element has operated
ELEMENT:
Auxiliary
overvoltage
AUX OV1 PKP
AUX OV1 DPO
AUX OV1 OP
Auxiliary overvoltage element has picked up
Auxiliary overvoltage element has dropped out
Auxiliary overvoltage element has operated
AUX OV2 to 3
Same set of operands as shown for AUX OV1
ELEMENT:
Auxiliary
undervoltage
AUX UV1 PKP
AUX UV1 DPO
AUX UV1 OP
Auxiliary undervoltage element has picked up
Auxiliary undervoltage element has dropped out
Auxiliary undervoltage element has operated
AUX UV2 to 3
Same set of operands as shown for AUX UV1
ELEMENT
Breaker flashover
BKR 1 FLSHOVR PKP A
BKR 1 FLSHOVR PKP B
BKR 1 FLSHOVR PKP C
BKR 1 FLSHOVR PKP
BKR 1 FLSHOVR OP A
BKR 1 FLSHOVR OP B
BKR 1 FLSHOVR OP C
BKR 1 FLSHOVR OP
BKR 1 FLSHOVR DPO A
BKR 1 FLSHOVR DPO B
BKR 1 FLSHOVR DPO C
BKR 1 FLSHOVR DPO
Breaker 1 flashover element phase A has picked up
Breaker 1 flashover element phase B has picked up
Breaker 1 flashover element phase C has picked up
Breaker 1 flashover element has picked up
Breaker 1 flashover element phase A has operated
Breaker 1 flashover element phase B has operated
Breaker 1 flashover element phase C has operated
Breaker 1 flashover element has operated
Breaker 1 flashover element phase A has dropped out
Breaker 1 flashover element phase B has dropped out
Breaker 1 flashover element phase C has dropped out
Breaker 1 flashover element has dropped out
BKR 2 FLSHOVR
Same set of operands as shown for BKR 1 FLSHOVR
ELEMENT
Breaker failure
BKR FAIL 1 RETRIPA
BKR FAIL 1 RETRIPB
BKR FAIL 1 RETRIPC
BKR FAIL 1 RETRIP
BKR FAIL 1 T1 OP
BKR FAIL 1 T2 OP
BKR FAIL 1 T3 OP
BKR FAIL 1 TRIP OP
Breaker failure 1 re-trip phase A (only for 1-pole schemes)
Breaker failure 1 re-trip phase B (only for 1-pole schemes)
Breaker failure 1 re-trip phase C (only for 1-pole schemes)
Breaker failure 1 re-trip 3-phase
Breaker failure 1 timer 1 is operated
Breaker failure 1 timer 2 is operated
Breaker failure 1 timer 3 is operated
Breaker failure 1 trip is operated
BKR FAIL 2 to 4
Same set of operands as shown for BKR FAIL 1
Summary of Contents for Multilin g60
Page 10: ...x G60 Generator Protection System GE Multilin TABLE OF CONTENTS INDEX ...
Page 32: ...1 22 G60 Generator Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Page 160: ...4 30 G60 Generator Protection System GE Multilin 4 3 FACEPLATE INTERFACE 4 HUMAN INTERFACES 4 ...
Page 486: ...5 326 G60 Generator Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Page 518: ...6 32 G60 Generator Protection System GE Multilin 6 5 PRODUCT INFORMATION 6 ACTUAL VALUES 6 ...
Page 532: ...7 14 G60 Generator Protection System GE Multilin 7 2 TARGETS 7 COMMANDS AND TARGETS 7 ...
Page 748: ...D 10 G60 Generator Protection System GE Multilin D 1 IEC 60870 5 104 APPENDIX D D ...
Page 760: ...E 12 G60 Generator Protection System GE Multilin E 2 DNP POINT LISTS APPENDIX E E ...