Illustration 5-19: Detector Chiller Thermo-Con - Orientation
Illustration 5-20: Fluoro UPS UL Layout (Optional)
The left, right or back side of the UPS cabinet can be positioned against the wall.
The front side of the UPS cabinet must be accessible for maintenance operation.
Clearance around the front should be sufficient to enable free passage of personnel with the
door fully opened.
Recommended minimum clearance between ceiling and top of the UPS should be 400 mm
(16”) for proper cooling air exhaust.