B
GFK-2731
Chapter B
B-7
B 1.5
Validation
Checklist for validating the VersaSafe system
Equipment identification
Date
Author
Test engineer
Remark
No. Requirement (mandatory)
Yes
Remark
1
Have the mandatory requirements for planning been met?
2
If applicable, have the mandatory requirements for startup been met?
3
Has validation of the safe devices used been carried out and are the results
available?
4
Are safety distances that must be observed calculated according to the
response and delay times implemented?
5
Have all the safety functions been checked successfully?
6
Do all the islands in the system have different island addresses?
7
Has it been ensured that in the overall system comprising VersaSafe and any
higher-level PROFIsafe system, the addresses (address within the VersaSafe
system and F-Address of the PROFIsafe system) are unique?
8
Has the VersaConf Safety project been printed with the project information
(name, CRC, time stamp, etc.)?
9
Has the CRC of the VersaConf Safety project printout been compared with the
CRC of the loaded project header and do they match?
No. Requirement (optional)
Yes No Remark
10
Are the directives and standards used listed in the declaration of conformity?
11
Has the safety logic created in VersaConf Safety been packed and archived?
Enter the archiving location (e.g., drive or cabinet) in the "Remark" column.
12
Has a complete printout of the safety logic configured in VersaConf Safety
been stored for the system?
13
Have all fully completed checklists been stored for the system?
Date
Signature (author)
Date
Signature (test engineer)