Checklist for configuration and parameterization of the VersaSafe system
Equipment identification
Date
Author
Test engineer
Remark
No. Requirement (mandatory)
Yes
Remark
1
Has the safety logic been configured?
2
Have all inputs and outputs been fully and correctly parameterized?
3
Are standard input signals exclusively used to configure standard operations
(e.g., for the enable principle using the EN_OUT block or for
acknowledgment)?
4
Has it been ensured that in the overall system comprising VersaSafe and any
higher-level PROFIsafe system, the addresses (address within the VersaSafe
system and F-Address of the PROFIsafe system) are unique?
5
Has watchdog time t
FWD
been set for each satellite according to the
application?
6
Has the correct terminal point been assigned to the correct signal?
7
Is the island address set correctly?
8
For IC220SDL953 outputs that are parameterized for two-channel operation,
are both channels parameterized correctly for each other?
9
For satellite inputs that are parameterized for two-channel operation, are both
channels parameterized correctly for each other?
10
For satellite outputs that are parameterized for two-channel operation, are both
channels parameterized correctly for each other?
11
Has the switch-off delay for stop category 1 been observed in the calculation of
the total response time for the machine/system?
12
Has prevention of undesired startup/restart been configured?
13
Has it been ensured that an operator acknowledgment can only be executed
by an intentional user action? (Not configured as "automatic".)
14
Has the checklist/project information been processed in VersaConf Safety
("Project... Project Info" menu item)?
No. Requirement (optional)
Yes No Remark
15
Date
Signature (author)
Date
Signature (test engineer)