T
ROUBLESHOOTING
REV7
/REV2
OI 250 (EN)
8.4
Replacing a Gas Connection
The standard gas connection consists of bent tubes. It is firmly
connected to the density monitor unit on one side. The other side
has a filling coupling with check valve for connection to the pole
columns.
The ends of the gas pipes (1) are flared (1a). The inner surface of
the flaring is the sealing surface. The gas pipes are connected by
union nuts (1b). The flaring allows the union nuts to be captivated
to the gas pipe.
The piping junction points (2) have an external thread and an inside
tapered contour (2a). The inside tapered contour forms the sealing
surface.
A tubular stiffener (3) stabilizes the joint mechanically. The O-ring
(4) fitted onto the stiffener seals the connection.
• Disconnect all filling connections. This will disconnect the gas
compartments of the pole columns from the gas piping.
• Unscrew the gas pipe that is to be replaced from the junction
points.
• Check the sealing surfaces of the junction points for damage.
• Apply grease to a new O-ring (4) as per L5 and fit onto the tubular
stiffener (3).
• Lubricate the sealing areas on the gas pipe and the junction
points as per L5.
In one equipment version, the switchgear is available with a gas
connection of type
FlexLink
.
The
FlexLink
technology makes it particularly easy to couple the
gas connections to the pole columns.
1
Gas pipe
1x
1a
Flaring
-
1b
Union nut
-
2
Junction point
-
2a
Inside tapered contour
-
3
Tubular stiffener
1x
4
O-ring
1x
1b
1a
3
1
4
2
2a
B
A
-P
-G
A
S
ROHR
Summary of Contents for GL 311 F3/4031 P/VE
Page 2: ......
Page 10: ...INTRODUCTION 10 146 OI 250 EN REV7 REV6...
Page 12: ...SAFETY 12 146 OI 250 EN REV7 REV3...
Page 48: ...INSTALLATION 48 146 OI 250 EN REV7 REV7...
Page 80: ...INSPECTION AND MAINTENANCE 80 146 OI 250 EN REV7 REV3...
Page 102: ...RECONDITIONING 102 146 OI 250 EN REV7 REV7...
Page 104: ...END OF LIFE MANAGEMENT 104 146 OI 250 EN REV7 REV2a...
Page 114: ...SPECIAL EQUIPMENT OPTIONAL 114 146 OI 250 EN REV7 REV0...
Page 128: ...REPLACEMENT PARTS AND ACCESSORIES 128 146 OI 250 EN REV7 REV6...
Page 130: ...HANDLING USED SULFUR HEXAFLUORIDE 130 146 OI 250 EN REV7 REV2...