1-2
C70 Capacitor Bank Protection and Control System
GE Multilin
1.1 IMPORTANT PROCEDURES
1 GETTING STARTED
1
This product is rated to Class A emissions levels and is to be used in Utility, Substation Industrial
environments. Not to be used near electronic devices rated for Class B levels.
1.1.2 INSPECTION PROCEDURE
1.
Open the relay packaging and inspect the unit for physical damage.
2.
View the rear nameplate and verify that the correct model has been ordered and delivered. The model number is at the
top right.
Figure 1–1: REAR NAMEPLATE (EXAMPLE)
3.
Ensure that the following items are included:
• Instruction manual (if ordered)
• GE EnerVista™ DVD (includes the EnerVista UR Setup software and manuals in PDF format)
• Mounting screws
4.
If there is any noticeable physical damage, or any of the contents listed are missing, contact GE Grid Solutions as fol-
lows.
GE GRID SOLUTIONS CONTACT INFORMATION AND CALL CENTER FOR PRODUCT SUPPORT:
GE Grid Solutions
650 Markland Street
Markham, Ontario
Canada L6C 0M1
TELEPHONE
:
Wor1 905 927 7070
Europe/Middle East/34 94 485 88 54
North America toll-free 1 800 547 8629
FAX
:
+1 905 927 5098
:
Worldwide [email protected]
Europe [email protected]
HOME PAGE
:
http://www.gegridsolutions.com/multilin
For updates to the instruction manual, firmware, and software, visit the GE Grid Solutions website.
834726A3.CDR
®
®
Model:
Mods:
Wiring Diagram:
Inst. Manual:
Serial Number:
Firmware:
Mfg. Date:
PO Num:
Item Num:
C70D00HCHF8AH6AL6BN8BU6AX7A
000
See manual
1601-9015
MAZB98000029
D
NOV 26, 2012
600001234.56
Control Power:
Contact Inputs:
Contact Outputs:
88-300V DC @ 35W / 77-265V AC @ 35VA
300V DC Max 10mA
Refer to Instruction Manual
RATINGS:
C70
- M A A B 9 7 0 0 0 0 9 9 -
Capacitor Bank Protection Relay
GE Multilin
- M A A B 9 7 0 0 0 0 9 9 -
LISTED
52TL
IND.CONT. EQ.
E83849
Summary of Contents for C70
Page 10: ...x C70 Capacitor Bank Protection and Control System GE Multilin TABLE OF CONTENTS ...
Page 394: ...5 270 C70 Capacitor Bank Protection and Control System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Page 676: ...E 10 C70 Capacitor Bank Protection and Control System GE Multilin E 1 OVERVIEW APPENDIX E E ...
Page 698: ...H 8 C70 Capacitor Bank Protection and Control System GE Multilin H 3 WARRANTY APPENDIX H H ...