Chapter 1 - Introduction
2.3.1
Meeting Site Ready Requirements
The site ready visit will take place at least three days prior to the delivery date. The site ready visit
is intended to verify that all of the siting requirement are met and the site is ready for installation.
The site ready visit will result in a report to the project manager indicating one of the following:
Pass
- All required items are present, completed and the site is ready for installation.
Conditional Pass
- is issued when 80% of all of the task are completed and all parties
agree that the 20% will be completed by the installation delivery date.
If a “Conditional Pass” is granted on the inspection date, the project manager must present
conclusive evidence that unfinished tasks are completed and that the site is ready for
delivery one business day prior to delivery.
Fail
- is issued when less than 80% of the task are completed and all parties cannot agree
that the remaining work will be completed by the requested installation delivery date.
Failed sites will be rescheduled when all items are completed.
2.3.2
Quick Installs
Quick installations are described as sites with minimum room improvements required. These
include, but are not limited to the following items:
•
Existing electrical disconnect device, wire size and grounds meet all of the above requirements.
•
Existing structural items including floor thickness meet all of the above requirements
•
Existing HVAC capacity and regulation meet all of the above requirements
•
Existing CT suite meets all of the above regulatory and minimum size requirements
•
Existing facility can accommodate the delivery and meet all of the above delivery requirements
Quick Installs are subject to the following restrictions:
•
Quick installs must have a new room print that accurately reflects the rooms to be upgraded.
•
Existing floor anchors from a non-BrightSpeed system CANNOT be reused.
•
New floor anchors must be a minimum of 4" from any existing floor penetrations.
Quick Installs typically involve a weekend de-install and room prep completion, with a next business
day delivery and install.
2.3.3
"Two-Step" and Upgrade Installs
A "Two-Step" installation is the practice of temporarily installing one CT system in a site with the
intention of upgrading the site to a different CT system at a later date.
•
For a "two-step" installation to be considered, the room must meet the minimum room
requirements for the project being upgraded.
•
As with any upgrade installation, "two-steps" are subject to ALL of the siting requirements
imposed by the upgrade/final system. This includes the recommended room size as well as
electrical, structural and HVAC requirements.
•
Two-steps and other upgrades may be done as "Quick" Installs. In this case, all requirements
described in Section 2.3.2 (above) also apply.
•
It is the customer’s responsibility to check that all requirements are met.
•
Rooms that do not meet the minimum requirements for the final product must either upgrade
(or enlarge) their room, or consider the "Left-Side Limited Access" option.