190-01639-00
GSU 75 ADAHRS Installation Manual
Rev. 6
Page 3-6
b) Solder the prepared wire assembly (items 3 and 8). Ensure a solid electrical connection
through the use of acceptable soldering practices. Slide a piece of shrink tube (item 1) onto
the prepared wire assembly and shrink using a heat gun. The chosen size of shrink tube must
accommodate the number of conductors present in the cable.
7. Install ring terminal (item 9)–After stripping an appropriate amount of insulation from the free end
of the 16 AWG pigtail wire (item 8), attach a ring terminal (item 9) to the end.
8. Install pins/sockets into connector (item 12)–Insert newly crimped pins/sockets and wires (items 3
and 11) into the appropriate connector location (item 12) as shown in
9. Connect the 16 AWG pigtail wire (item 8) to connector (item 12).: Join the ring terminal (item 9)
to the strain relief (item 7) using the screws (item 10) provided in the GSU 75 Connector Kit
(GPN: 011-03109-00). Tighten the screws (item 10).
10. Secure cables– Refer to
to verify that all required pins/sockets have been attached to
the cables and fully inserted into the correct slots of the connector. It is recommended to wrap the
cable bundle with Silicone Fusion Tape (GPN: 249-00114-00 or a similar version) at the point
where the connector strain relief and connector will contact the cable bundle. The smooth side of
the strain relief should contact the tape.
Figure 3-2 GTP 59 Sensor - GSU 75 Interconnect Harness
1
11
7
13
10
9
3
4
2
6
5
8
12
340095
The document reference is online, please check the correspondence between the online documentation and the printed version.