Page 9-2
G300 Installation Manual – Post Installation Checkout and Calibration Procedures
Revision A
190-00921-01
9.1
Required Test Equipment
The following test equipment is required to conduct and complete all post installation checkout
procedures in this section: (All test equipment should have current calibration records)
•
Pitot/static ramp tester
•
Digital Multi-Meter (DMM)
•
Ground power unit capable of supplying 14/28 Vdc power to the aircraft systems and avionics
•
Outdoor line-of-site to GPS satellite signals or GPS indoor repeater
•
Digital Level or equivalent
9.2
GDU 37X Test Procedure
Test the GPS Receiver:
1.
Power on unit and use the FMS Joystick to select the Info Page.
2.
Verify that the GPS receiver is functional and able to calculate its present position.