14
|
www.gd-elmorietschle.com
© Gardner Denver Schopfheim GmbH, Gardner Denver Deutschland GmbH
Installation
5
Installation
5.1 Preparing for installation
Check the following points:
• Machine freely accessible from all sides
• Do not close ventilation grids and holes
• Sufficient room for installing and removing pipes
and for maintenance work, particularly for install-
ing and dismantling the machine
• No external vibration effects
• Do not suck any hot exhaust air from other ma-
chines into the cooling system.
The suction flange (Fig. 2/D), oil filling point (Fig. 2/H), oil sight glass (Fig. 2/I), oil outlet (Fig. 2/K),
gas ballast (Fig. 2/U) a the oil removing device housing (Fig. 2/T) must be easily accessible.
The cooling air inlets (Fig. 2/E) and the cooling air outlets (Fig. 2/F) must be at least 30 cm away
from adjacent walls. Cooling air coming out must not be sucked in again.
For maintenance work there must be a space of at least 50 cm around the machine.
5.2 Installation
NOTICE
The machine may only be operated when it is
set up horizontally.
Material damage resulting from the machine
tipping over and falling.
When installed at more than 1000 m above sea
level a reduction in power is noticeable. In this
case we would ask you to contact us.
Ensure that the foundation complies with the follow-
ing conditions:
• Level and straight
• The bearing surface must be at least the same
size as the machine
• The bearing surface must be able to bear the
weight of the machine
It is possible to install the machine on a firm base without anchoring. When installing on a substruc-
ture we recommend fixing with flexible buffers