Revision 5
135
August 2021
8.3
QA Document Package Check List and Requirements
Table 34 is completed during the manufacturing process and QA inspection to ensure that the
all relevant operations are performed.
Table 34: Document Package Checklist
Serial Number: _______________
Description
Initial
Date
Sample System Pressure Checked - System Heaters
Sample System Pressure Checked – Sample System
Purge System Checked
Aspirator Performance Tested
Gas Runs Complete (Calibration Data Sheet)
Temperature Sensor Inputs Checked and Calibrated
Analog Output Calibration Checked
Digital Output Checked
System 24VDC Supply Checked
Span Factor Set
Condenser Solenoid Function Checked
Zero Solenoid Function Checked
Control Cabinet Air Solenoid Function Checked
Operation of Cell Heaters Checked
Burn Oven for three (3) weeks
Cell Pressure Transducer Checked.
Dielectric Strength Test Certificate Completed
Matrix and Cal Documents Completed
Serial Numbers Recorded
Oven Lid Latches Adjusted and Locked
Summary of Contents for 943-TGS-CE
Page 137: ...Revision 5 137 August 2021 Figure 84 Oven Cabinet Details...
Page 138: ...Revision 5 138 August 2021 Figure 85 Control Cabinet Door Closed...
Page 139: ...Revision 5 139 August 2021 Figure 86 Control Cabinet Door Removed...
Page 140: ...Revision 5 140 August 2021 Figure 87 Power Steam Air Signals Connection Details...
Page 141: ...Revision 5 141 August 2021 Figure 88 AC Wiring Schematic...
Page 142: ...Revision 5 142 August 2021 Figure 89 DC Signals and Wiring Diagram...
Page 143: ...Revision 5 143 August 2021 Figure 90 Flow Diagram...
Page 144: ...Revision 5 144 August 2021 Figure 91 Control and Oven Cabinets Interconnect Wiring...