Technical information 

1a   METAL consumer unit must be installed by a qualified electrician in accordance with the current IET Wiring Regulations 
       BS 7671 
1b    Total load must not exceed the rating of the incoming isolator or any additional limitation. 
1c    The total sum of the individual MCBs may exceed this value where there is appropriate diversity in the installation. 
1d    The Consumer Unit and associated components have been manufactured to the following specifications:

         

 

 

Standards (TABLE 1) 

 

 

 

Torque Settings (TABLE 2) 

Device 

Standard 

Consumer Unit 

EN 61439-3 

Main Switch 

IEC EN 60947-3 

RCD 

IEC EN 61008-1 

MCB 

IEC EN 60898-1 

RCBO 

IEC EN 61009-1 

IP RATING 

IP2XC 

 

1e    Ambient Temperature: MCBs are calibrated at 30°C according to the calibration temperature requirements of EN60898. At 

other temperatures the following rating factors should be used: 

 At 60°C  0.85    At 20°C  1.0    At 0°C   1.15

 

1f    

Adjacent thermal-magnetic MCBs should not be continuously loaded at their nominal rated currents when mounted in 

enclosures.

 We recommend a 60% de-rating factor is applied to the MCBs nominal rated current where it is intended to 

load the MCBs continuously 

2    Enclosure Mounting 

2a    Remove front cover. 
2b    Remove 

minimum

 appropriate 

knockouts with a punch, in order to maintain the IP rating and fire containment of the 

enclosure we recommend glands are used.

 

2c   Fix base to wall using screws and rawl plugs as appropriate 

and remove any debris from inside the consumer unit

.  

2d   Adjust to the square. 
2e   Route incoming cables to desired positions. 

3    Connection of Tails 

 

3a    Cut and dress the main incoming cables and earth conductor. 
3b    Connect into the appropriate terminals 

(1)

  & N

 (3) on RCD, earth terminal bar and torque (TABLE 2). 

4   Connections 

4a    Cut, dress and connect circuit conductors to appropriate MCB neutral and earth terminals. 
4b   ALL CONNECTIONS (including factory made connections) MUST BE TORQUED (TABLE 2). 
4c    

Make sure that each earth and neutral outgoing circuit is correctly made to the corresponding numbered terminals as 

this will ensure final testing and fault finding is easier.

 

5    Circuit Identification 

5a    All circuits must be clearly labelled on the front cover.  

6     Enclosure Earthing 

6a

 

An earth cable is supplied in the accessory pack which must be fitted between the front cover and the earth terminal bar 
for earth continuity.

 

7     Operation of the TEST button on RCD

 

7a      When newly fitted systems do not trip on the TEST button of the RCD or using the RCD tester the problem is normally 
caused by an earth to neutral fault on the circuit (PME supply). 

8    Testing  

8a    After completion of the installation, it must be tested in accordance with the latest edition of the IET Wiring 
        Regulations for Electrical Installations (BS 7671). 

 
 
 

Before fitting the front cover, check all connections including factory made connections are TORQUED. 
Loose connections can cause fires!!!! 

 

Device 

Max Cable 

Capacity 

Recommended 

Torque 

RCD 

35mm² 

2.5Nm 

MCB 

16mm² 

2.5Nm 

Earth Neutral Terminals 

16mm² 

2.0Nm 

® 