Installing/Removing the Rack Model into the Rack
Hardware Installation
–
The operability of the safety mechanisms at the server e.g. stoppers or
holding back systems must be guaranteed.
–
The form of the rack support uprights must ensure the frontal screwing on of
the rails.
–
Frontally bolted telescopic rails or sliding rails.
The rails are provided with a linear alignment possibility to ensure also an
adjustment to different rack depths.
–
No support of the cable management (delivered with the mounting kit).
–
Climatic conditions.
For the ventilation of the installed server a large extent unhindered air intake
in the rack front and air discharge in the rear cover of the rack are necessary.
In principle the ventilation concept plans that the necessary cooling is
reached by the horizontal self-ventilation of the installed devices (air flow
from the front to the rear).
–
Power supply.
For the installation in 3rd-Party Racks it is to be made certain that appro-
priate socket strips are present.
4.4.1
Mounting into the PRIMECENTER Rack
For mounting the server into the PRIMECENTER Rack the following parts are
necessary:
–
support bracket
–
two telescopic rails (assembled)
–
possibly four assembly brackets (VL; VR; HL; HR are punched onto the
brackets)
–
eight mounting springs or plugwashers (figure 5 on page 34)
I
To ensure the frontal assembling of the telescopic rails to the support
bracket and/or to the support uprights assembly brackets are supplied.
If none assembly brackets are supplied the telescopic rails are frontally
fastened on the support bracket and/or on the support uprights.
I
General information are provided in the Technical Manual for the PRIME-
CENTER Rack (see also “Related Publications” on page 107).