![Fujitsu PRIMERGY CX400 M6 Upgrade And Maintenance Manual Download Page 20](http://html.mh-extra.com/html/fujitsu/primergy-cx400-m6/primergy-cx400-m6_upgrade-and-maintenance-manual_121047020.webp)
Step
included
Explanation
Server shutdown
no
Shutdown time depends on hardware and
software configuration and may vary
significantly.
Software tasks necessary before
maintenance, see
Rack removal,
disassembly
yes
Making the server available, removing the
server from the rack (if applicable).
Transport
no
Transporting the server to the service table
(where required) depends on local
customer conditions.
Maintenance
procedures
yes
Maintenance procedures including
preliminary and concluding software tasks.
Transport
no
Returning the server to its installation site
(where required) depends on local
customer conditions.
Assembly, rack
installation
yes
Reassembling the server, installing the
server in the rack (if applicable).
Starting up
no
Booting time depends on hardware and
software configuration and may vary
significantly.
Table 1: Calculation of the average task duration
2.4
Tools you need at hand
When preparing the maintenance task, ensure that all required tools are
available. You will find a list of required tools at the beginning of each
procedure.
Before you start
20
Upgrade and Maintenance Manual
CX400 M6