Chapter 2 Installing the Tape Library
2.2 Unpacking the Tape Library
FUJITSU Storage ETERNUS LT40 S2/LT60 S2 LTO Library Installing, Starting Up and Maintaining
Copyright 2018 FUJITSU LIMITED
P3AM-5392-07ENZ0
21
2.2
Unpacking the Tape Library
Before you begin, clear a work surface to unpack the library. Select an open 2U rack location allowing easy
access to the host server and an easily accessible power outlet.
Unpacking the library:
Procedure
1
Before opening and removing the library from the shipping container, inspect the container
for shipping damage. If you notice any damage, report it to the shipping company
immediately.
2
Open the box and remove the two rack rails (if included) and set aside.
3
Carefully remove the shipping materials from the top of the library. Remove the accessory
package and set aside.
4
Lift the library out of the carton and remove the bag from the library. Remove the foam
cushion from the back of the library. Save the packaging materials for future use.
End of procedure
CAUTION
If the temperature in the room where the library will be installed varies by more
than 15
C (30
F) from the room where the library was stored, allow the library to
acclimate to the surrounding environment for at least 12 hours before unpacking
it from the shipping container.
CAUTION
Do not place the library on either end or sides as this may damage the library.
After unpacking the library, save all the original packing materials in case you need to ship or move the
library later.
Summary of Contents for ETERNUS LT40 S2
Page 2: ...This page is intentionally left blank ...
Page 110: ......