11-21
11.1 Cutter/Feed Section
11
3. Remove the E-ring and then the guide plate.
Reinstallation
Reinstallation is essentially in the reverse order of removal.
Removal
1. Remove the emulsion surface side upper cutter
2. Remove the two springs.
3. Remove the E-ring, bearing and then the roller.
Installation
Installation is essentially in the reverse order of removal.
Removal
1. Remove the emulsion surface side upper cutter
2. Remove the screw and then the sensor (D631)
bracket.
3. Remove the four screws and then the guide plate.
Reinstallation
Reinstallation is essentially in the reverse order of removal.
LII064
E-ring
Guide Plate
11.1.21
Upper Cutter Nip Roller Replacement
LII065
Springs (2)
E-ring
Bearings
Roller
11.1.22
Back Surface Side Upper Cutter Entrance Guide Plate Removal/Reinstallation
LII066
Screw
Sensor Bracket
Screws (4)
Guide Plate