Closing and commissioning the inverter
Closing the in-
verter's connec-
tion area/hous-
ing cover, and
commissioning
NOTE!
The housing cover is fitted with a lock for safety reasons, which allows the hous-
ing cover on the inverter to be pivoted only when the DC disconnector is
switched off.
▶
Only clip and pivot the housing cover onto the inverter when the
DC discon-
nector is switched off
.
▶
Do not use excessive force to clip in and pivot the housing cover.
1
Place the cover on the connection
area. Tighten the five screws by rotat-
ing them 180° to the right in the indic-
ated order using a screwdriver (TX20).
2
Clip the housing cover onto the invert-
er from above.
Press on the lower part of the housing
cover and tighten the two screws 180°
to the right using a Torx screwdriver
(TX20).
Turn the DC disconnector to the "On"
switch position. Switch on the auto-
matic circuit breaker. For systems with
a battery, observe the switch-on se-
quence according to chapter
on page
.
IMPORTANT!
Open WLAN access
point with the optical sensor, see
chapter
Starting the in-
verter for the
first time
When using the inverter for the first time, various setup settings must be con-
figured.
If the setup process is cancelled before the process is complete, any data that
has been input up to this point is lost and the start screen with the installation
wizard is shown again. If the process is interrupted, such as in the event of a
power outage, the data is saved. Commissioning may be continued from the point
at which the process was interrupted once the power supply has been restored. If
the setup was interrupted, the inverter feeds energy into the grid at maximum
500 W and the operating status LED flashes yellow.
95
EN
Summary of Contents for Primo GEN24 3.0
Page 2: ......
Page 12: ...12...
Page 13: ...General information 13...
Page 14: ...14...
Page 34: ...34...
Page 35: ...Backup power variant PV Point OP 35...
Page 36: ...36...
Page 38: ...38...
Page 39: ...Backup power variant Full Backup 39...
Page 40: ...40...
Page 48: ...48...
Page 49: ...Installation 49...
Page 50: ...50...
Page 57: ...Do not install the inverter on the ceiling 57 EN...
Page 101: ...Settings user interface of the in verter 101...
Page 102: ...102...
Page 132: ...132...
Page 133: ...Options 133...
Page 134: ...134...
Page 144: ...144...
Page 145: ...Appendix 145...
Page 146: ...146...
Page 172: ...172...
Page 173: ...Circuit diagrams 173...
Page 174: ...174...
Page 175: ...Circuit Diagram PV Point OP Circuit Diagram 175 EN...
Page 176: ...Fronius Primo GEN24 and BYD Battery Box Premium HV Circuit Diagram 176...
Page 179: ...Automatic switch to backup power 1 pin double separation e g Austria Circuit Diagram 179 EN...
Page 180: ...Automatic switch to backup power 1 pin single separation e g Australia Circuit Diagram 180...
Page 181: ...Automatic switch to backup power 2 pin double separation e g Germany Circuit Diagram 181 EN...
Page 182: ...Automatic switch to backup power 2 pin single separation e g France Spain Circuit Diagram 182...
Page 183: ...Automatic switch to backup power 2 pin double separation e g UK Circuit Diagram 183 EN...
Page 185: ...Fronius Primo GEN24 with Enwitec Box Circuit Diagram 185 EN...
Page 186: ...Wiring diagram surge protective device SPD Circuit Diagram 186...
Page 187: ...Dimensions of the inverter 187...
Page 188: ...188...
Page 189: ...Fronius Primo GEN24 3 6 kW Fronius Primo GEN24 3 6 kW 189 EN...
Page 190: ...190...
Page 191: ...191 EN...
Page 192: ......