![Froling Turbomat TM 400 Installation Instructions Manual Download Page 20](http://html1.mh-extra.com/html/froling/turbomat-tm-400/turbomat-tm-400_installation-instructions-manual_2338738020.webp)
❒ Ensure the complete assembly is level by adjusting the feet (spanner size SW
30 mm)
➥ Check that none of the adjustable feet are loose
❒ Slide the insulation sheet steel panels (1) on both sides under the heat exchanger
and feed through the pins (2)
4.5.3 Assembling the stoker unit
❒ Secure the stoker duct to the slide-on duct using 4 M10x40 bolts and M10 nuts
❒ Secure the flange plate with 4 M10x20 bolts and M10 nuts
❒ Fix the rotary valve or the burn back flap (depending on the version) in place using
four M12 screws and nuts.
➥ Fit the burn back flap so that the pivot point of the flap is on the side opposite
the boiler.
❒ Push in the stoker screw
❒ Fit the flange plate onto the stoker screw and align it parallel to the stoker duct
flange
➥ Check that the stoker screw can turn freely
4
Assembly
Installing the boiler
20
Fröling GesmbH | 4710 Grieskirchen, Industriestraße 12 | www.froeling.at