6.2.2 Non-permitted fuels
The use of fuels other than those defined in the "Permitted fuels" section, and particularly
the burning of refuse, is not permitted
NOTICE
In case of use of non-permitted fuels:
Burning non-permitted fuels increases the cleaning requirements and leads to a
build-up of aggressive sedimentation and condensation, which can damage the
boiler and also invalidates the guarantee! Using non-standard fuels can also lead
to serious problems with combustion!
For this reason, when operating the boiler:
r
Use only the permitted fuels
6.3 Heating up for the first time
NOTICE
Optimum efficiency and efficient, low-emission operation can only be guaranteed if the
system is set up by trained professionals and the standard factory settings are observed.
Take the following precautions:
r
Initial startup should be carried out with an authorised installer or with Froling
customer services
The customer is responsible for ensuring the following prior to initial start-up of the
system by Froling customer services:
▪ Electrical installation
▪ Installation of water pipes
▪ Connect flue gas including all insulation work
▪ Work must comply with local fire protection regulations
The operator must ensure the following conditions are met for initial start-up:
r
The network can take at least 50% of the boiler's nominal output.
r
The discharge system must be empty – "dry run" of system.
Ä
Fuel must be available, however, so that the discharge system can be filled once
the system is released.
r
It is essential that the electrician who has carried out the installation work is available
when starting up the system for the first time to make any changes to the wiring which
may become necessary.
r
Ensure that those responsible for operating the system are present.
Ä
During initial start-up, operating staff are shown how to use the boiler. It is
imperative for proper handover of the product that those involved are present as
this is a one-off opportunity.
If the fireclay in the combustion chamber needs to be screed dried:
r
Provide the following quantities of dry firewood:
Ä
Systems up to 250 kW: ¼ m³
Ä
Systems up to 500 kW: ½ m³
Ä
Systems up to 1500 kW: 1 m³