4 Assembly
4.1 Transport and handling
The discharge system is part-assembled and comes packed on a pallet.
❒
Follow the transport instructions on the packaging!
A door should be provided in the store or a ceiling opening in the silo for bringing in
the unit
❒
Observe the stirring head diameter of 1300 mm!
To prevent damage:
❒
Transport components, particularly drive components, with care
4.1.1 Temporary storage
If the system is not going to be assembled immediately:
❒
Store components at a protected location, which is dry and free from dust
➥
Damp can lead to damage to individual parts, particularly in the motor!
4.2 Installation site
When planning the fuel store, you should observe the following design information:
1
2
3
4
5
6
Store detail
Design information
1
Walls and
ceilings
The walls and ceilings of the store and the boiler room must be fire-proof
(REI 90) in compliance with local regulations
2
Hole in
wall
Do not fix or cement the transfer trough and rotary agitator duct to the
brickwork as this can create a bridge transferring all mechanical noise and
vibrations to the brickwork. For this reason any gaps around holes made in
walls must be filled with insulating material in compliance with the
standards ÖNORM B 3836 or DIN 4102-11.
For dimensions of the opening see “Hole in wall”
Assembly
4
Transport and handling