4.3.3 Installation with recessed bulk chute
If the filling system is operated with a stationary recessed bulk chute, the following
design information should be noted:
1
2
1
Protective structure to prevent operator from reaching over during operation.
Dimensioning of structure acc. to EN ISO 13857.
2
Cover over filling area to prevent operator from climbing in during operation.
Dimensioning of structure acc. to EN ISO 13857.
The following figure shows an example of how the bulk chute can be executed in the
filling area. It is important that the user can see into the filling area for the entire filling
process. The material should be transferred to the bulk chute on the opposite side.
1
Operating position within view of the bulk chute
2
Protective structure to prevent operator from reaching over during operation
3
Cover over filling area to prevent operator from climbing in during operation
Assembly
4
Installation site
Installation- and Operating Intructions BFSV / BFSU | M1420116_en
29