www.franklinfueling.com
PN & Rev:
0000210C
E - m a i l :
t e c h @ f r a n k l i n f u e l i n g . c o m
F A X 1 - 2 0 7 - 2 8 2 - 9 0 0 2
T E L 1 - 8 0 0 - 9 8 4 - 6 2 6 6
P AG E
1 o f
2
s a l e s @ f r a n k l i n f u e l i n g . c o m
F A X 1 - 2 0 7 - 2 8 3 - 0 1 5 8 T E L 1 - 8 0 0 - 8 7 2 - 3 4 5 5
REPLACEMENT
PART
INSTRUCTIONS
Memory Backup Battery Replacement Instructions
for Tank Sentinel, AutoStik, & BulkStik ATGs
Parts & Materials
Required:
One
new
3 volt lithium
battery (INCON P/N:
TSSP-BAT / 390-0004), a
thin piece of adhesive tape,
and a digital multimeter with
test probes.
Diagram:
Testing the
Battery ( B1 )
Use a digital multimeter set
to read 5 DC volts and
measure the DC voltage
between the
+
battery
terminal and
–
ground or
the yellow-colored metal
shield
(+2.8 to +3.3 volts DC is good).
When to Test the
Battery Voltage (Schedule)
: Yearly after the first two years of operation or use.
DANGER Electrical Shock Hazard.
Make sure all safety shields are installed to
prevent electrical shocks —
DO NOT
touch any device other than the battery.
Removal & Installation Steps
( with Tank Gauge Power ON & SW 1 ON ):
1.)
Printout the complete system and tank setup reports
for all tanks. (
Note
– if the
power goes out or is turned off while the battery is out of its holder then all of the
setup/programmed values of the system will be lost. If this happens then the entire
tank gauge will have to be reprogrammed ).
WEDGE UP HERE
ABOUT 1/8 INCH
Battery Cutaway
Side View
b
PRY OUT HERE
a
Yellow
colored
metal
shield
b
TS-1001/N-N U10
VER No. DATE
a
Replace the battery if the voltage reading is below
2.8 volts DC