5. START-UP AND OPERATION

Guidelines for System Connection 

It  is  recommended  to  use  flexible  hoses  on  the  water  exchanger 
connections. 

It  is  recommended  to  install  vent  valves  at  the  highest  point  of  the 
system. 

The  system should be executed  so that,  in the case of a failure,  it is 
possible to disassemble the device. For this purpose it is best to use 
shut-off valves just by the device.

 

The  system  with  the  heating  medium  must  be  protected  against  an 
increase of the heating medium pressure above the permissible value 
(1.6 MPa).

 

While screwing exchanger to pipeline - connecting stubs has to be hold 
by wrench. 

Start Up 

Before connecting the power supply check the correctness of connection 
of  the  fan  motor  and  the  controllers.  These  connections  should  be 
executed in accordance with their technical documentation. 

Before connecting the power supply check whether the mains voltage is 
in accordance with the voltage on the device data plate. 

Before  starting  the  device  check  the  correctness  of  connection  of  the 
heating medium conduits and the tightness of the system. 

The  electrical  system  supplying  the  fan  motor  should  be  additionally 
protected  with  a  circuit  breaker  against  the  effects  of  a  possible  short-
circuit in the system.

 

Starting the device without connecting the ground conductor is forbidden.

Operation 

The  device  is  designed  for  operation  inside  buildings,  at  temperatures 
above 0

o

C. In low temperatures (below 0ºC) there is a danger of freezing 

of the medium. 

The  manufacturer  bears  no  responsibility  for  damage  of  the  heat 
exchanger  resulting  from  freezing  of  the  medium  in  the  exchanger.  If 
operation of the device is expected at temperatures lower than 0º, then 
glycol  solution  should  be  used  as  the  heating  medium,  or  special 
automatic systems should be used for protecting against freezing of the 
medium in the exchanger. 

It is forbidden to place any objects on the heater or to hang any objects 
on the connecting stubs. 

The  device  must  be  inspected  periodically.  In  the  case  of  incorrect 
operation of the device it should be switched off immediately. 

It  is  forbidden  to  use  a  damaged  device.  The  manufacturer  bears  no 
responsibility for damage resulting from the use of a damaged device. 

If  it is necessary  to clean the exchanger, be careful not to  damage the 
aluminium lamellas. 

For the time of performing inspection or cleaning the device, the electrical 
power supply should be disconnected.

In case water is drained from the device for a longer period of time, the 
exchanger tubes should be emptied with compressed air.

It  is  not  allowed to  make  any  modification  in  the unit.  Any  modification 
causes in warranty loss. 

 

Periodic inspections 

To  keep  proper  technical  parameters  Flowair  recommends  periodic 
service (every 6 months) of fan heaters on behalf of the user. 
During inspections user should: 

Check heat exchanger, if is it filled with  dirt or dust. If necessary - use 
pressurized air stream to clean the exchanger’s lamellas, 

Check heat exchanger, if is it filled with  dirt or dust. If necessary - use 
pressurized air stream to clean the exchanger’s lamellas, 

Check fan blades, in case of dirt use damp cloth and remove dirt, 

Check bracket installation,

Check heat exchanger and hydraulic connection correctness,

Check wires insulation, 

Check power supply, 

Check medium flow, 

Check levelling of the unit.

Summary of Contents for L1

Page 1: ...LEO S1 I S2 I S3 BMS L1 I L2 I L3 BMS XL2 I XL3 BMS INOX ST EN FAN HEATER TECHNICAL DOCUMENTATION OPERATION MANUAL SV Fläktluftvärmare Teknisk Dokumentation Drift och Underhålls manual ...

Page 2: ...grams 10 5 Start Up and Operation 13 6 Service and warranty terms 17 7 Conformity with WEEE directive 2012 19 UE 19 Innehållsförteckning 1 Inledning 4 2 Teknisk Data 6 3 Installation 9 3 1 Installation Konsol 9 3 2 Monteringsanvisningar 9 3 3 U Profiler 10 10 4 Kopplingsschema 5 Uppstart och Drift 14 6 Underhålls och Garanti 17 7 Certifiering med WEEE direktivet 2012 19 UE 19 ...

Page 3: ...arbonate HCOᵌ 60 300 mg l Ammonium 1 0 mg L Sulphide 0 05 mg L Chloride Cl 100 mg l Med LEO fläktluftvärmare får man ett värmesystem med en god spridning Luft strömmar genom och värmeväxlas med varm vatten i värmepaketet Fläktluftvärmare används främst till att värma upp stora byggnader med stora volymer som industrilokaler lager och kommersiella lokaler Höljet på en standard LEO är gjort av utvid...

Page 4: ...oC Max temperatur vatten o C 120 INOX ST 130 Max operating pressure MPa Maximal drifttryck MPa 1 6 Connection Anslutnings dimension 1 2 Installation Installation Indoor Inomhus Max working temperature o C Maximal arbetstemperatur o C 60 Device mass kg Vikt kg 9 5 INOX 13 1 ST 13 1 10 4 INOX 13 8 ST 13 8 10 8 INOX 14 3 ST 14 3 Mass of device filled with water kg Vikt med vatten kg 10 2 INOX 13 8 ST...

Page 5: ...peratur vatten oC 120 INOX ST 130 Max operating pressure MPa Maximal drifttryck MPa 1 6 Connection Anslutnings dimension 3 4 Installation Installation Indoor Inomhus Max working temperature oC Maximal arbetstemperatur oC 60 Device mass kg Vikt kg 14 9 INOX 19 4 ST 19 4 16 2 INOX 20 8 ST 20 8 17 8 INOX 22 7 ST 22 7 Mass of device filled with water kg Vikt med vatten kg 15 9 INOX 20 4 ST 20 4 18 2 I...

Page 6: ...T 130 Max operating pressure MPa Maximal drifttryck MPa 1 6 Connection Anslutnings dimension 3 4 Installation Installation Max working temperature oC Maximal arbetstemperatur oC 60 Device mass kg Vikt kg 23 2 INOX 29 9 ST 29 9 26 2 INOX 34 2 ST 34 2 Mass of device filled with water kg Vikt med vatten kg 25 9 INOX 32 6 ST 32 6 30 3 INOX 38 3 ST 38 3 Acoustic pressure level has been measured 5m from...

Page 7: ...n be mounted to vertical or horizontal partitions in any position During the montage the minimal distances from the walls and ceiling have to be kept 3 INSTALLATION Fläktluftvärmarna kan monteras vertikalt eller horisontellt Vid montage måste minsta avstånd från vägg och tak erhållas 3 1 INSTALLATION BRACKET 3 1 INSTALLATION KONSOL 3 2 ASSEMBLY INSTRUCTIONS 3 2 MONTERINGS INSTRUKTIONER M8 screws a...

Page 8: ...profiles should be mounted in corners as drawing shows Is not allowed to screw profiles in other places U profiler skall alltid monteras i hörnen på Fläktluftvärarna se bild 4 CONNECTION DIAGRAMS 4 KOPPLINGSSCHEMA 3 3 U PROFIL Alternativ lösning ...

Page 9: ...ontroller or BMS you have to binary set addresses on each each DRV must have individual address DRV module by DIP switch SW1 To address modules check if the power supply is turned off than set then the addresses as shown in the table than turn on the power supply SV Vid anslutning av DRV modul till T box kontroll eller BMS måste olika adresser sättas på varje DRV modul Detta görs genom att slå til...

Page 10: ...moduler till en och samma T box kontroll EN DRV modules can be connected to the BMS Building Management System SV DRV moduler kan anslutas direkt till BMS Building Managemnet System WARNING The connection must be carried out with 3 wire recommended UTP to connectors DRV IN VARNING Anslutning måste ske med en 3 trådig kabel till DRV IN rekommenderat UTP BMS GBS ...

Page 11: ...ger resulting from freezing of the medium in the exchanger If operation of the device is expected at temperatures lower than 0º then glycol solution should be used as the heating medium or special automatic systems should be used for protecting against freezing of the medium in the exchanger It is forbidden to place any objects on the heater or to hang any objects on the connecting stubs The devic...

Page 12: ...r ej för frysskador på värmeväxlaren om temperaturen på mediet understigit 0oC Om enheten skall användas vid lägre temperaturer understigande 0oC bör glykol användas som medie eller så bör systemet automatiseras som så att inga frysskador på värmeväxlaren kan uppstå Det är föbjudet att placera föremål uppe på värmaren samt att hänga saker i anslutningarna Enhetens bör kontrolleras periodvis Om eve...

Page 13: ...n please contact the manufacturer s service department The manufacturer bears no responsibility for operating the device in a manner inconsistent with its purpose by persons not authorised for this and for damage resulting from this Made in Poland Made in EU Manufacturer FLOWAIR GŁOGOWSKI I BRZEZIŃSKI SP J ul Chwaszczyńska 135 81 571 Gdynia tel 48 58 669 82 20 e mail info flowair pl www flowair co...

Page 14: ...rektywami normami and harmonized norms with above directives en geharmoniseerde normen met de bovenstaande richtlijnen а также в соединении с данными директивами стандартами PN EN ISO 12100 2012 Bezpieczeństwo maszyn Ogólne zasady projektowania Ocena ryzyka i zmniejszanie ryzyka Safety Of Machinery General Principles For Design Risk Assessment And Risk Reduction Veiligheid van Machines Basisbegrip...

Page 15: ...e with the rules for the disposal of electrical equipment Unit name LEO Capacity control 3 speed Model Item Symbol Value Unit LEO S1 Heating capacity P rated h 2 7 kW LEO S2 5 7 LEO S3 7 0 LEO L1 6 9 LEO L2 10 8 LEO L3 13 9 LEO XL2 20 2 LEO XL3 25 7 heating capacity for parameters inlet water temp 45 C water temperature drop 5 C room air temp 20 C Model Item Symbol Value Unit LEO S1 Total electric...

Page 16: ...16 www flowair com 56072 MT DTR LEO SLXL EN PL NL RU V3 ...

Reviews: