Connecting the Unit Syrup Line
The syrup lines attached at the lower back of
the cabinet connect the eight bags of syrup to
the Blending Assembly, with the ninth tube
connecting the Sanitizer Tank to the Blending
Assembly.
1. Locate the 9-Tube Lead at the back of the
cabinet. Remove the dust cap and slide the
coupler casing toward the unit to expose the
lead line coupler.
2. Connect the 9-Tube Lead with the 9-Tube
Assembly, with the 9-hole gasket in
between. Align the 9-hole gasket with the
coupler pins of the 9-Tube Lead and place
the gasket against the coupler. Then align
the coupler pins of the two tube assemblies
and connect them.
3. Slide the coupler casing over the connection
and screw each coupler nut into each end of
the casing. Tighten the coupler nuts to
secure the connection.
Installing & Filling the Sanitizer Tank
Use only NSF approved sanitizer solution
mixed according to the manufacturer’s
instructions in the Sanitizer Tank. The tank
system delivers solution to specific areas of the
Flavor Burst
®
system such as the syrup lines
during certain functions. In order to utilize
these clean-in-place functions, keep an
adequate supply of approved sanitizer solution
in the Sanitizer Tank at all times.
The Sanitizer Tank should be checked on a
daily basis. For proper sanitation, keep only
FRESH sanitizer solution in the tank. Some
sanitizer solutions may become ineffective after
a few days and may not clear the system of all
bacteria present. See the sanitizer
manufacturer’s information for potency and
longevity. Replace older solution with fresh
solution when necessary. Additionally, use hot
water when mixing the sanitizer solution, as it
will be much more effective in cleaning the
system.
1. Prepare approximately 3 gallons (11.5
Liters) of approved sanitizer solution
according to manufacturer’s instructions.
2. Insert one end of the sanitizer tube into the
fitting located at the lower back of the
cabinet.
3. Insert the other end of the sanitizer tube into
the fitting on the Sanitizer Tank.
9-HOLE GASKET
COUPLER PINS
26431
Summary of Contents for JBT 80FCB-2B
Page 4: ...3 PAGE INTENTIONALLY LEFT BLANK...
Page 7: ...6 PAGE INTENTIONALLY LEFT BLANK...
Page 9: ...8 General System Overview Figure 1...
Page 15: ...14 Syrup Pump and Related Parts Figure 4 6 7 5 8 9 10 4 3 26004 1 1D 1C 1A 1E 1B 2 2B 2A 2D 2C...
Page 19: ...18 Cabinet Electronics Figure 6...
Page 22: ...21 2B 3B Jumbo Touch Panel Electronics See Figure 7...
Page 23: ...22 2B 3B Jumbo Touch Panel Electronics Figure 7...
Page 26: ...25 4B Jumbo Touch Panel Electronics See Figure 8...
Page 27: ...26 4B Jumbo Touch Panel Electronics Figure 8...
Page 44: ...43 PAGE INTENTIONALLY LEFT BLANK...