Commissioning
1. Follow the instructions below regarding any parts that are included in your unit.
Start by switching off the electricity supply.
2. Check that the unit is horizontal.
3. Check that the inspection doors open and close smoothly. Adjust the hinges if necessary.
4. Check that the unit is clean on the inside and outside.
5.
Dampers with actuators
– Check that the connected dampers are in the closed position when the stepper
motor is in its end position.
6.
Filter
– Check that the filter cassettes are in place and the locking system is closed.
7.
Rotor
– Check that the rotary heat exchanger rotates easily when pushed manually. If it does not, the rotor
on the eQ PRIME 023-050 can be adjusted.
8.
Manometers and flow metering instruments
– Check that the instruments are set on 0 and
connected correctly (+/–) to the test points.
9. For checking other functions, follow separate instructions.
10. Check that all the safety restraints have been removed.
11. Switch on the main power switch.
12. The basic control system settings are factory configured, but certain settings must be customised for each
installation. Finish configuring the control system using the handheld terminal. See page 13 for further details.
a) Log in. Password 2000
b) Set desired language
c) Set date and time
d) Set fan control setpoints
e) Set temperature setpoints
f)
Set final pressure drop for the filters
g) Set desired operating period
13. Set the operating switch to Auto. See page 15 for further details.
14. Adjust the duct system and the air terminal devices.
15. Adjust the unit's pressure balance, see page 12.
16. If the unit has active mixing. Run 0-calibration. See section Active mixing.
Questions and answers, page 51
Alarm guide, page 54